Question

Problem 4-16 Contrasting ABC and Conventional Product Costs [LO4-2, LO4-3, LO4-4] [The following information applies to...

Problem 4-16 Contrasting ABC and Conventional Product Costs [LO4-2, LO4-3, LO4-4]

[The following information applies to the questions displayed below.]

For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.20 hours of direct labor time per unit and only a small amount of machining. Manufacturing overhead costs are currently assigned to products on the basis of direct labor-hours.

Despite the growing popularity of the company’s new LEC 90, profits have been declining steadily. Management is beginning to believe that there may be a problem with the company’s costing system. Direct material and direct labor costs per unit are as follows:

LEC 40 LEC 90
Direct materials $ 26.00 $ 48.00
Direct labor (0.20 hours and 0.60 hours @ $15.00 per hour) $ 3.00 $ 9.00

Management estimates that the company will incur $1,040,000 in manufacturing overhead costs during the current year and 80,000 units of the LEC 40 and 40,000 units of the LEC 90 will be produced and sold.

Problem 4-16 Part 1

Required:

1-a. Compute the predetermined overhead rate assuming that the company continues to apply manufacturing overhead cost on the basis of direct labor-hours.

1-b. Using this rate and other data from the problem, determine the unit product cost of each product.

Homework Answers

Answer #1

1-a. Compute the predetermined overhead rate assuming that the company continues to apply manufacturing overhead cost on the basis of direct labor-hours.

Estimated labour hours = (80000*.20+40000*.60) = 40000 Hour

Overhead rate = 1040000/40000 = $26 per labour hour

1-b. Using this rate and other data from the problem, determine the unit product cost of each product.

LEC 40 LEC 90
Direct material 26 48
Direct labour 3 9
Overhead 26*.2 = 5.2 26*.6 = 15.6
Unit Cost 34.20 72.60
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.60 hours of direct labor...
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.40 hours of direct labor...
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.20 hours of direct labor...
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.40 hours of direct labor...
Contrasting ABC and Conventional Product Costs Rocky Mountain Corporation makes two types of hiking boots—Xactive and...
Contrasting ABC and Conventional Product Costs Rocky Mountain Corporation makes two types of hiking boots—Xactive and Pathbreaker, Data concerning these two product lines appear below: Xactive Pathbreaker Direct materials per unit $64.80 $51.00 Direct labor costs per unit $18.20 $13.00 Direct labor -hours per unit 1.4 DLHs 1.0 DLHs Estimated annual production and sales 25,000 units 75,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing...
Exercise 4-8 Computing ABC Product Costs [LO4-2, LO4-3] [The following information applies to the questions displayed...
Exercise 4-8 Computing ABC Product Costs [LO4-2, LO4-3] [The following information applies to the questions displayed below.] Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:     Direct Labor-Hours per unit Annual Production Rims 0.70 26,000 units Posts 0.70 90,000 units Additional information about the company follows: Rims require $14 in direct materials per unit, and Posts require $10. The direct labor wage rate is $18 per hour. Rims are more complex to...
Foundational [LO4-1, LO4-2, LO4-3, LO4-4] Greenwood Company manufactures two products—14,000 units of Product Y and 6,000...
Foundational [LO4-1, LO4-2, LO4-3, LO4-4] Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining...
Problem 10A-8 Applying Overhead; Overhead Variances [LO10-3, LO10-4] Lane Company manufactures a single product and applies...
Problem 10A-8 Applying Overhead; Overhead Variances [LO10-3, LO10-4] Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $4.60 per direct labor-hour and the budgeted fixed manufacturing overhead is $1,935,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $9.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.30 per...
Exercise 4-3 Compute ABC Product Costs [LO4-3] Larner Corporation is a diversified manufacturer of industrial goods....
Exercise 4-3 Compute ABC Product Costs [LO4-3] Larner Corporation is a diversified manufacturer of industrial goods. The company's activity-based costing system contains the following six activity cost pools and activity rates: Activity Cost Pool Activity Rates Labor-related $ 7.00 per direct labor-hour Machine-related $ 4.00 per machine-hour Machine setups $ 50.00 per setup Production orders $ 100.00 per order Shipments $ 150.00 per shipment General factory $ 4.00 per direct labor-hour    Cost and activity data have been supplied for...
Exercise 3-8 Computing ABC Product Costs [LO3-2, LO3-3] [The following information applies to the questions displayed...
Exercise 3-8 Computing ABC Product Costs [LO3-2, LO3-3] [The following information applies to the questions displayed below.] Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:     Direct Labor-Hours per unit Annual Production   Rims 0.60         22,000 units      Posts 0.20         80,000 units        Additional information about the company follows: a. Rims require $14 in direct materials per unit, and Posts require $10. b. The direct labor wage rate is $15...