The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows:
Standard Costs
Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.72 per hour
Variable overhead 3 hours per unit at $1.99 per hour
Actual Costs
Total variable cost, $17,800
Total fixed cost, $7,900
The total factory overhead cost variance is
Total factory overhead cost variance = Total actual cost - Total standard cost
Total actual cost = Total variable cost + Total fixed cost
= $17,800 + $7,900
= $25,700
Total standard cost = Total standard variable cost + Total standard fixed costs
= (2,900 units * 3 hours per unit * $1.99) + (2,900 units * 3 hours per unit * $0.72)
= $17,313 + $6,264
= $23,577
Total factory overhead cost variance = $25,700 - $23,577
= $2,123 (U)
Variance is unfavorable because actual cost is more than the standard cost.
Get Answers For Free
Most questions answered within 1 hours.