Question

FIXED OVERHEAD SPENDING AND VOLUME ARIANCES, COLUMNAR AND FORMULA APPROACHES A company provided the following information:...

FIXED OVERHEAD SPENDING AND VOLUME ARIANCES, COLUMNAR AND FORMULA APPROACHES

A company provided the following information:

Standard fixed overhead rate (SFOR) per direct labour hour    $7.00

Actual fixed overhead rate (AFOR) per direct labour hour        $6.95

Actual direct labour hours worked (AH)                                      36,100

Actual production in units                                                              12,000

Standard hours allowed for actual units produced (SH)          36,000

Required:

  1. Using the columnar approach, calculate the fixed overhead spending and efficiency variances.

  1. Using the formula approach, calculate the fixed overhead spending variance.

  1. Using the formula approach, calculate the fixed overhead efficiency variance.
  1. Calculate the total fixed overhead variance.

Homework Answers

Answer #1

SOLUTION

1.

A. AH * AFOR

= 36,100 * $6.95 = $250,895

B. AH * SFOR

= 36,100 * $7.00 = $252,700

C, SH * SFOR

= 36,000 * $7.00 = $252,000

Spending variance = A-B

= $250,895 - $252,700 = $1,805 F

Volume variance = B-C

= $252,700 - $252,000 = $700 U

2. Fixed overhead spending variance = (AFOR - SFOR) * AH

= ($6.95 - $7.00) * 36,100

= 0.05 * 36,100

= $1,805 F

3. Fixed overhead efficiency variance = (AH - SH) * SFOR

= (36,100 - 36,000) * $7.00

= 100 * $7.00

= $700 U

4.

Fixed overhead spending variance $1,805 F
Fixed overhead efficiency variance $700 U
Total fixed overhead variance 1,105 F
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Variable Overhead Spending and Efficiency Variances, Columnar and Formula Approaches Rath Company provided the following information:...
Variable Overhead Spending and Efficiency Variances, Columnar and Formula Approaches Rath Company provided the following information: Standard variable overhead rate (SVOR) per direct labor hour $3.75 Actual variable overhead costs $222,816 Actual direct labor hours worked (AH) 57,200 Actual production in units 15,000 Standard hours (SH) allowed for actual units produced 60,000 Required: 1. Using the columnar approach, calculate the variable overhead spending and efficiency variances. Enter amounts as positive numbers. (1) (2) (3)                   Spending Efficiency...
Calculating the Fixed Overhead Spending and Volume Variances Standish Company manufactures consumer products and provided the...
Calculating the Fixed Overhead Spending and Volume Variances Standish Company manufactures consumer products and provided the following information for the month of February: Units produced 131,300 Standard direct labor hours per unit 0.2 Standard fixed overhead rate (per direct labor hour) $2.20 Budgeted fixed overhead $64,800 Actual fixed overhead costs $68,700 Actual hours worked 26,500 Required: 1. Calculate the fixed overhead spending variance using the formula approach. Calculate the volume variance using the formula approach. What if 127,300 units had...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)   ...
  Standard variable overhead rate per hour $1   Standard fixed overhead rate per hour $2   Planned monthly...
  Standard variable overhead rate per hour $1   Standard fixed overhead rate per hour $2   Planned monthly activity 40,000 machine hours   Actual production completed 82,000 units   Standard machine processing time Two units per hour   Actual variable overhead $37,000   Actual total overhead $121,000   Actual machine hours worked 40,500                   All of the company's overhead is variable or fixed in nature.                                      Required:                   1.     Calculate the spending and efficiency variances for variable overhead.                   2.     Calculate the SPENDING and PRODUCTION volume variances for fixed overhead.
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
The following information describes a company’s direct labor usage in a recent period. Actual direct labor...
The following information describes a company’s direct labor usage in a recent period. Actual direct labor hours used (AH) 65,000 Actual direct labor rate per hour (AR) $ 15 Standard direct labor rate per hour (SR) $ 13 Standard direct labor hours for units produced (SH) 66,900 AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate Compute the direct labor rate and efficiency variances for the period and classify each as favorable or...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...