Question

The following costs were incurred on the construction of a new building for X Inc: Land...

The following costs were incurred on the construction of a new building for X Inc: Land $800,000 Clearing and grading 50,000 closing costs 25,000 architect fees 25,000 building permits 10,000 building costs 1,965,000 paving and sidewalks 60,000 landscaping 40,000 property tax lien 25,000 X Inc took out a construction loan to cover the entire project at the same time the land was purchased. Three month after the land was purchased, the construction on the building began. The construction period took twelve more month. Total interest costs for the entire loan were $300,000. Required: 1) calculate the costs of the land, buildings and land improvements, including the amount of capitalized interest on the building 2) If an independent constructor could have completed the building costs for $100,000 less than costs incurred by X Inc, would you adjust the fair market value of the building? Explain

Homework Answers

Answer #1

1) Costs of Land, Buildings and land improvements-

Land 800000

Clearing and Grading 50000

Closing costs 25000

Architect fees 25000

Building Permits 10000

Building cost 1965000

Paving and sidewalks 60000

Landscaping 40000

Property tax 25000

Interest on Loan 300000

Total 3300000

2) If an independent constructor could have completed the building cost for $100000 than also FMV of similar property would have been same. The lesser incurred cost is profit to independent constructor.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Bordewick, Inc. purchased land and incurred the following costs: Purchase price $500,000, Clearing and grading costs...
Bordewick, Inc. purchased land and incurred the following costs: Purchase price $500,000, Clearing and grading costs $50,000, Demolition costs on old building $12,500, Broker fees to execute purchase $10,000, Cost of a new parking lot $25,000. What is the cost recorded for the land account? A. $597,500 B. $572,500 C. $562,500 D. $550,000
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: Purchase price of the land $ 1,290,000 Demolition and removal of old building 89,000 Clearing and grading the land before construction 195,000 Various closing costs in connection with acquiring the land 51,000 Architect's fee for the plans for the new building 59,000 Payments to Maxtor...
Benedict Company incurred the following costs. 1. Sales tax on factory machinery purchased 2. Painting of...
Benedict Company incurred the following costs. 1. Sales tax on factory machinery purchased 2. Painting of and lettering on truck immediately upon purchase 3. Installation and testing of factory machinery 4. Real estate broker’s commission on land purchased 5. Insurance premium paid for first year’s insurance on new truck 6. Cost of landscaping on property purchased 7. Cost of paving parking lot for new building constructed 8. Cost of clearing, draining, and filling land 9. Architect’s fees on self-constructed building...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $1 million, respectively. Shortly after acquisition, Samtech spent $83,000 to construct a parking lot and $41,000 for landscaping. Required: 1. Determine the initial valuation of each asset Samtech acquired in these transactions. 2. Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $260,000 and the salvaged materials were sold for $6,500. In...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at...
An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.5 and $1.5 million, respectively. Shortly after acquisition, Samtech spent $97,000 to construct a parking lot and $55,000 for landscaping. Required: 1. Determine the initial valuation of each asset Samtech acquired in these transactions. 2. Determine the initial valuation of each asset, assuming that immediately after acquisition, Samtech demolished the building. Demolition costs were $400,000 and the salvaged materials were sold for $8,500. In...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 26,000 Legal fees for drawing the contract 5,000 Pro-rated property taxes for the period after acquisition 46,000 State transfer fees 5,000 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.2 and $1.8 million, respectively. Shortly after acquisition, Samtech spent...
Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its...
Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $258,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 275,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was outstanding for the...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 35,000 Legal fees for drawing the contract 9,500 Pro-rated property taxes for the period after acquisition 55,000 State transfer fees 5,900 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.6 and $1.2 million, respectively. Shortly after acquisition, Samtech spent...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT