Talamoto Co. manufactures a single product that goes through two processes — mixing and cooking. The following data pertains to the Mixing Department for September. Work-in-process Inventory Sept. 1 32,000unitsConversion complete 70%Work-in-process inventory Sept. 30 23,000unitsConversion complete 50%Units started into production in Sept. 103,000 Units completed and transferred out ?unitsCosts Work-in-process inventory Sept.1 Material P$171,000 Material Q 157,000 Conversion 171,000 Costs added in September Material P$257,000 Material Q 236,000 Conversion 506,900 Material P is added at the beginning of work in the Mixing Department. Material Q is also added in the Mixing Department, but not until units of product are forty percent completed with regard to conversion. Conversion costs are incurred uniformly during the process.The cost of goods completed and transferred out under the weighted-average method is calculated to be: (Do not round your intermediate calculations.)
Multiple Choice
$1,498,900.
$1,295,902.
$1,194,302.
$1,270,302.
$1,225,302.
Answer: $1,295,902
Calculations:
Units completed and transferred out = Units in Beginning WIP + Units started during the period - Units in ending WIP = 32,000 + 103,000 - 23,000 = 112,000 units
Equivalent Units | |||
Materials | Conversion | ||
Units completed and transferred out | 112000 | 112000 | |
Ending work in process: | |||
Materials [23,000 x 100%] | 23,000 | ||
Conversion [ 23,000 x 50%] | 11,500 | ||
Total equivalent units | 135,000 | 123,500 | |
Cost per equivalent unit | |||
Materials | Conversion | Total Cost | |
Cost of Beginning WIP | $328,000 | $171,000 | |
Cost added during the period | $493,000 | $506,900 | |
Total cost | $821,000 | $677,900 | |
÷ Total equivalent units | 135,000 | 123,500 | |
=Cost per unit | $6.08 | $5.49 | $11.57 |
Cost of units completed and transferred out = 112,000 x $11.57 = $1,295.,902
Get Answers For Free
Most questions answered within 1 hours.