Question

Iron Inc. manufactures fertilizers by mixing two chemicals, A and B. The standard cost information for...

Iron Inc. manufactures fertilizers by mixing two chemicals, A and B. The standard cost information for 1 bag of fertilizer is given as follows: Material A 3lb. @ $7 per pound Material B 7lb. @ $5 per pound For 2012, the firm produced 1,890 bags of fertilizer. It used 7,000 pounds of material A and 13,000 pounds of material B. The actual price of both A and B was $4.50 per pound. Required: Calculate the material mix variance of the 2012 production. Denote a favorable variance with a positive number and unfavorable variance with a negative number.

Homework Answers

Answer #1
Working Note 1 A B Total
Actual Input 7000 13000
Standard Price $            7.00 $            5.00
Total $ 49,000.00 $ 65,000.00 $ 114,000.00
Working Note 2 A B Total
Standard MIX for 1 bag 0.30 0.70
Actual Inputs 7000 13000 20000
Actual Inputs at Standard Mix 6000 14000
Standard Price $            7.00 $            5.00
Total $ 42,000.00 $ 70,000.00 $ 112,000.00


MIx Variance = Note 2 - Note 1 = $112000 - $114000 = $2000 Adverse

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Johnson Corporation produces fertilizers by combining chemicals X and Y. The standard cost for a bag...
Johnson Corporation produces fertilizers by combining chemicals X and Y. The standard cost for a bag of fertilizer is: Material X 3lb at $4 per lb. Material Y 7lb at $5 per lb. For 2020 Johnson Corporation manufactured 1890 bags of fertilizer. They used 7000lbs of material X and 13000lbs of material Y. Actual price of both X and Y was $4 per pound. What is Johnson Corpoations's material mix variance?
a.) Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000...
a.) Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 5.00 yards at $5.75 per yard Direct labor of 3.00 hours at $16.00 per hour Overhead applied per sleeping bag at $16.00 In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.90 per yard. The labor used was 11,700 hours at an...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 4.50 yards at $5.50 per yard Direct labor of 2.50 hours at $20.00 per hour Overhead applied per sleeping bag at $16.00 In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.70 per yard. The labor used was 11,700 hours at an average...
The following cost information is for Leslie Company. Actual results Total cost of purchasing material $58,000...
The following cost information is for Leslie Company. Actual results Total cost of purchasing material $58,000 Number of labor hours worked 1,000 hours Number of material pounds used in production 5,850 pounds Total labor cost $48,000 Number of units produced 280 units Number of material pounds purchased 6,250 pounds Leslie Company has established the following standards. Price per pound of materials $10.00 per pound Number of pounds of material to produce one unit 20 pounds Standard labor rate $50.00 per...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 6.00 yards at $5.00 per yard Direct labor of 3.00 hours at $20.00 per hour Overhead applied per sleeping bag at $17.00 In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.70 per yard. The labor used was 11,700 hours at an average...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 5.50 yards at $5.00 per yard Direct labor of 2.50 hours at $20.00 per hour Overhead applied per sleeping bag at $18 In the month of April, the company actually produced 5,100 sleeping bags using 26,800 yards of material at a cost of $5.10 per yard. The labor used was 13,250 hours at an average...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 5.00 yards at $5.75 per yard Direct labor of 2.50 hours at $19.00 per hour Overhead applied per sleeping bag at $18.00 In the month of April, the company actually produced 4,900 sleeping bags using 24,100 yards of material at a cost of $5.90 per yard. The labor used was 11,500 hours at an average...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 4.00 yards at $6.00 per yard Direct labor of 2.50 hours at $19.00 per hour Overhead applied per sleeping bag at $18.00 In the month of April, the company actually produced 4,900 sleeping bags using 25,100 yards of material at a cost of $5.70 per yard. The labor used was 11,500 hours at an average...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping...
Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 5.00 yards at $5.50 per yard Direct labor of 3.00 hours at $16.00 per hour Overhead applied per sleeping bag at $18.00 In the month of April, the company actually produced 4,900 sleeping bags using 25,700 yards of material at a cost of $6.10 per yard. The labor used was 11,500 hours at an average...
Taylor Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping...
Taylor Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows: Direct material of 5.50 yards at $5.50 per yard Direct labor of 3.00 hours at $20.00 per hour Overhead applied per sleeping bag at $17.00 In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.70 per yard. The labor used was 11,700 hours at an average...