Required information
[The following information applies to the questions displayed below.]
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March):
Molding | Fabrication | Total | |||||||
Estimated total machine-hours used | 2,500 | 1,500 | 4,000 | ||||||
Estimated total fixed manufacturing overhead | $ | 14,500 | $ | 17,700 | $ | 32,200 | |||
Estimated variable manufacturing overhead per machine-hour | $ | 3.20 | $ | 4.00 | |||||
Job P | Job Q | |||||
Direct materials | $ | 31,000 | $ | 17,000 | ||
Direct labor cost | $ | 35,400 | $ | 14,700 | ||
Actual machine-hours used: | ||||||
Molding | 3,500 | 2,600 | ||||
Fabrication | 2,400 | 2,700 | ||||
Total | 5,900 | 5,300 | ||||
Sweeten Company had no underapplied or overapplied manufacturing overhead costs during the month.
Required:
For questions 1-8, assume that Sweeten Company uses a plantwide predetermined overhead rate with machine-hours as the allocation base. For questions 9-15, assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments.
12. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations.)
overhead rate | |||||||
Molding | |||||||
Fixed manufacturing overhead | (14500/2500)= | 5.8 | |||||
Variable manufacturing overhead | 3.2 | ||||||
total predetermined overhead rate | 9 | ||||||
Fbrication | |||||||
Fixed manufacturing overhead | (17700/1500) | 11.8 | |||||
Variable manufacturing overhead | 4 | ||||||
total predetermined overhead rate | 15.8 | ||||||
Job P | |||||||
Direct materials | 31000 | ||||||
Direct labor cost | 35,400 | ||||||
overhead applied | |||||||
Molding | (9*3500) | 31500 | |||||
Fabrication | (15.8*2400) | 37920 | |||||
total overhead | 135820 | ||||||
unit product cost = | 135820/20 | ||||||
6791 |