Question

QDM Question 5 (17 marks): A company is attempting to decide the mix of products which...

QDM Question 5 : A company is attempting to decide the mix of products which it should produce next week. It has six products, each with a unit profit (unit profit =selling price –variable cost per unit) and a unit production time as shown below:

Product

Profit ($/unit)

Production time (hours/unit)

1

10

1

2

22

2

3

35

1.7

4

19

2.4

5

55

4.5

6

115

9.5

The company has 720 hours available next week. The company has the following additional linear constraints:

  • If any of the above six products are produced a fixed cost of $1000 is incurred.
  • If product 3 is produced, 40 hours are needed for production setup.

Formulate an integer programming model to find next week production schedule at maximize profit with linear objective function and all linear constraints.

Decision variables (1 mark):

Objective function (1 mark):

Constraints :

Additional constraint 1 : Product 1 must be produced if any of Product 2, 3 and 4 is produced.

Additional constraint 2 : Product 3 must be produced if all of Product 4, 5 and 6 are produced.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
(Laker Steel) Laker Steel considers a product mix problem with three products and three constraints. Let...
(Laker Steel) Laker Steel considers a product mix problem with three products and three constraints. Let X1 = units of product 1, X2 = units of product 2, and X3 = units of product 3. The constraints below must be satisfied. (1) At most 60 labor hours are available. (2) At most 120 pounds of materials are available. (3) At least 10 units of product 2 must be produced. An LP was formulated as follows: max 30 X1 + 10...
10) Natural Furniture Company manufactures three outdoor products, chairs, benches, and tables. Each product must pass...
10) Natural Furniture Company manufactures three outdoor products, chairs, benches, and tables. Each product must pass through the following departments before it is shipped: sawing, sanding, assembly, and painting. The time requirements (in hours) are summarized in the tables below. The production time available in each department each week and the minimum weekly production requirement to fulfill contracts are as follows: Minimum Capacity Production Department (In Hours) Product Level Sawing 450 Chairs 100 Sanding 400 Benches 50 Assembly 625 Tables...
A company produces two models of products, SUPER and ULTRA. Each SUPER model generates a profit...
A company produces two models of products, SUPER and ULTRA. Each SUPER model generates a profit of $8, and each ULTRA model generates a profit of $5. The table below shows how many minutes are required to produce each model on two different machines with maximum available time. How many products of each model must be produced to maximize profit? How much is the maximum profit? SUPER ULTRA Time Available Machine 1 3 minutes 2 minutes 360 minutes Machine 2...
Company A makes 2 models of radios. Model 1 provides a profit of $54 for each...
Company A makes 2 models of radios. Model 1 provides a profit of $54 for each unit, while model 2 provides a profit of $72. Two units materials will be required to make one model 1 Radio, while model 2 needs four units. In addition a model 1 takes 4 hours of the time to produce and model 2 takes 5 hours. If 100 units of raw materials and 140 hours of production times are available, how many of each...
Choosing the Optimal Product Mix with a Constrained Resource and a Demand Constraint Billings Company produces...
Choosing the Optimal Product Mix with a Constrained Resource and a Demand Constraint Billings Company produces two products, Product Reno and Product Tahoe. Each product goes through its own assembly and finishing departments. However, both of them must go through the painting department. The painting department has capacity of 2,460 hours per year. Product Reno has a unit contribution margin of $120 and requires 5 hours of painting department time. Product Tahoe has a unit contribution margin of $75 and...
Local Steel Construction Company produces two products, steel and wood beams. Steel beams have a unit...
Local Steel Construction Company produces two products, steel and wood beams. Steel beams have a unit contribution margin of $200, and wood beams have a unit contribution margin of $150. The demand for steel beams exceeds Local Steel Construction Company's production capacity, which is limited by available direct labor and machine-hours. The maximum demand for wood beams is 90 per week. Management desires that the product mix should maximize the weekly contribution toward fixed costs and profits. Direct manufacturing labor...
A company manufactures two products: large fans and medium fans. Each large fan requires 3 hours...
A company manufactures two products: large fans and medium fans. Each large fan requires 3 hours of wiring and 2 hours of drilling. Each medium fan requires 2 hours of wiring and 1 hour of drilling. There are 480 hours of wiring time available and 280 hours of drilling time available. Each large fan yields a profit of $25. Each medium fan yields a profit of $18. The company wants to manufacture at least 20 large fans. The objective is...
Ficcus Inc. manufactures two types of products, the Gx and the Tx models. The company operates...
Ficcus Inc. manufactures two types of products, the Gx and the Tx models. The company operates five days per week and makes a net profit of $125 on the Gx model, and $175 on the Tx model. The models are manufactured in two main departments: production and assembly. The production department has 58 skilled workers, each of whom works 7 hours per day. The assembly department has 25 workers, who also work a 7-hour shift. On an average, to produce...
Atlas Inc. produces product A and product B. Each product must go through two processes. Each...
Atlas Inc. produces product A and product B. Each product must go through two processes. Each A produced requires two hours in process 1 and five hours in process 2. Each B produced requires six hours in process 1 and three hours in process 2. There are 80 hours of capacity available each week in each process. Each A produced generates $6.00 in profit for the company. Each B produced generates $9.00 in profit for the company. The constraint for...
Exercise 20-17 Tharp Company operates a small factory in which it manufactures two products: C and...
Exercise 20-17 Tharp Company operates a small factory in which it manufactures two products: C and D. Production and sales results for last year were as follows. C D Units sold 9,000 19,900 Selling price per unit $94 $75 Variable cost per unit 53 39 Fixed cost per unit 20 20 For purposes of simplicity, the firm averages total fixed costs over the total number of units of C and D produced and sold.    The research department has developed a...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT