Question

Consider the following selected cost data for the Pittsburgh Forging Company for 2018. Budgeted manufacturing overhead...

  1. Consider the following selected cost data for the Pittsburgh Forging Company for 2018. Budgeted manufacturing overhead costs $7,500,000

Budgeted machine-hours 250,000

Actual manufacturing overhead costs $7,300,000

Actual machine-hours 245,000

The company uses normal costing. Its job-costing system has a single manufacturing overhead cost pool. Costs are allocated to jobs using a budgeted machine-hour rate.

1. Compute the budgeted manufacturing overhead rate. (1pt)

2. Compute the amount of under- or overallocation of manufacturing overhead. Prepare a journal entry to dispose of this amount. (1pt)

  1. Parker Company produces mathematical and financial calculators and operates at capacity. Data related to the two products are presented here:

Mathematical

Financial

Annual production in units

50,000

100,000

Direct material costs

$150,000

$300,000

Direct manufacturing labor costs

$ 50,000

$100,000

Direct manufacturing labor-hours

2,500

5,000

Machine-hours

25,000

50,000

Number of production runs

50

50

Inspection hours

1,000

500

Total manufacturing overhead costs are as follows:

Total Machining costs             $375,000

Setup costs                              $120,000

Inspection costs                      $105,000

1. Choose a cost driver for each overhead cost pool and calculate the manufacturing overhead cost per unit for each product. (1.5 pt)

2. Compute the manufacturing cost per unit for each product using Activity-based Costing.(2 pts)

  1. Freddie and Jason have just opened the Texas Toothpick, a chain-saw sharpening and repair service located on Elm Street. The Texas Toothpick promises same-week repair service. Freddie and Jason are concerned that a projected dramatic increase in demand as the end of October nears will cause service to deteriorate. Freddie and Jason have had difficulty attracting employees, so they are the only workers available to complete the work.

Safety considerations require that they each work no more than 40 hours per week. The first chain-saw sharpening and repair required 7 hours of work, and an 80 percent learning curve is anticipated.

Week                                      Units               Cumulative Units

October 2–6                            8                                  8

October 9–13                          19                                27

October 16–20                        10                                37

October 23–27                        27                                64

a. How many total hours are required to complete 64 chain saws?(0.5pt)

b. How many hours of work are required for the week ending on Friday the 13th? (1pt)

c. Will Freddie and Jason be able to keep their same week service promise during their busiest week just before Halloween?(2pts)

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Texas Co. established the following overhead cost pools and cost drivers: Budgeted Estimated Overhead Cost Pool...
Texas Co. established the following overhead cost pools and cost drivers: Budgeted Estimated Overhead Cost Pool Overhead Cost Driver Cost Driver Level Quality controls $780,000 # of inspections 26,000 inspections Machine setups $720,000 # of setups 12,000 setups Other overhead costs $900,000 # of machine hrs 50,000 machine hrs Total overhead costs $2,400,000 A recent order for sailboats used: Quality inspections 750 inspections Machine setups 500 setups Machine hours (MHs) 2,400 machine hours Required: a. What is the overhead rate...
4-24 Budgeted manufacturing overhead rate, allocated manufacturing overhead. Gammaro Company uses normal costing. It allocates manufacturing...
4-24 Budgeted manufacturing overhead rate, allocated manufacturing overhead. Gammaro Company uses normal costing. It allocates manufacturing overhead costs using a budgeted rate per machine-hour. The following data are available for 2017: Budgeted manufacturing overhead costs $4,600,000 Budgeted machine-hours      184,000 Actual manufacturing overhead costs $4,830,000 Actual machine-hours      180,000 Required: Calculate the budgeted manufacturing overhead rate. Calculate the manufacturing overhead allocated during 2017. Calculate the amount of under- or overallocated manufacturing overhead. Why do Gammaro’s managers need to calculate this amount?
Q7. Trini Inc. bases its manufacturing overhead budget on budgeted direct labor-hours. The direct labor budget...
Q7. Trini Inc. bases its manufacturing overhead budget on budgeted direct labor-hours. The direct labor budget indicates that 9,100 direct labor-hours will be required in May. The variable overhead rate is $2.60 per direct labor-hour. The company's budgeted fixed manufacturing overhead is $100,440 per month, which includes depreciation of $8,910. All other fixed manufacturing overhead costs represent current cash flows. The May cash disbursements for manufacturing overhead on the manufacturing overhead budget should be? Q8. The following data pertains to...
The Zef Radiator Company uses a​ normal-costing system with a single manufacturing overhead cost pool and​...
The Zef Radiator Company uses a​ normal-costing system with a single manufacturing overhead cost pool and​ machine-hours as the​ cost-allocation base. The following data are for 2017​: Budgeted Manufacturing Overhead Costs $ 4,875,000 Overhead Allocation Base machine-hours Budgeted machine-hours 75,000 Manufacturing Overhead Costs Incurred $ 5,125,000 Actual machine-hours 80,000 Machine-hours data and the ending balances​ (before proration of​ under- or overallocated​ overhead) are as​ follows: Actual Machine-Hours 2017 End-of-Year Balance Cost of Goods Sold 60,000 $ 8,500,000 Finished Goods Control...
Buller Company uses normal costing. It allocates manufacturing overhead costs using a budgeted rate per machine-hour....
Buller Company uses normal costing. It allocates manufacturing overhead costs using a budgeted rate per machine-hour. The following data are available for 2019: Budgeted manufacturing overhead costs $4,800,000 Budgeted machine-hours 180,000 Actual manufacturing overhead costs $3,990,000 Actual machine-hours 150,000 Required: 1. Calculate the budgeted manufacturing overhead rate. 2. Calculate the manufacturing overhead allocated during 2019. 3. Calculate the amount of under- or overallocated manufacturing overhead. Why do Buller’s managers need to calculate this amount?
Determine the cost to manufacture this product: Budgeted Manufacturing Overhead       $960,000 Budgeted Direct Labor Hours                 &
Determine the cost to manufacture this product: Budgeted Manufacturing Overhead       $960,000 Budgeted Direct Labor Hours                    62,000 Budgeted Machine Hours                          54,420 Assume that the company incurs: $179 in Direct Materials Costs used 30 direct labor hours at $12 per hour uses direct labor hours as the cost driver
Wings Co. budgeted $569,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing...
Wings Co. budgeted $569,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level for Cost Driver Overhead Cost Driver Materials handling $ 184,000 4,600 pounds Weight of materials Machine setup 15,900 530 setups Number of setups Machine repair 1,200 30,000 machine hours Machine hours Inspections 21,000 300 inspections Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor 20 hours Direct materials 190...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct labor-hour rate for the actual direct labor hours. Any overallocated or underallocated overhead is written-off to the cost of goods sold at the end of the month. During April 2019, ABC Manufacturing recorded the following: Budgeted manufacturing overhead costs: $400,000 Budgeted direct labor-hours: 20,000 DLHRS Budgeted machine hours: 16,000 MHRS Actual manufacturing overhead costs: $360,000 Actual direct labor-hours:   22,500 DLHRS Actual machine hours: 15,000...
Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly Finishing Manufacturing overhead...
Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly Finishing Manufacturing overhead costs $ 1,120,800 $ 510,000 Direct labor hours 11,100 DLH 19,100 DLH Machine hours 5,100 MH 15,100 MH 1. What is the company's single overhead rate based on direct labor hours? Estimated overhead costs       per direct labor hour Estimated direct labor hours 2. What is the company's single plantwide overhead rate base on machine hours? Estimated overhead costs per machine hour Estimated...
The controller established the following overhead cost pools and cost drivers: Overhead Cost Pool Budgeted Overhead...
The controller established the following overhead cost pools and cost drivers: Overhead Cost Pool Budgeted Overhead Cost Driver Estimated Cost Driver Level Machine setups $207,000 # of setups 180 setups Material handling 138,000 # of pounds 12,000 Quality control 245,000 # of inspections 1,000 inspections Other overhead cost 220,000 # of machine hrs 20,000 machine hrs An order of steel tubing used the following amounts of the cost drivers: # of setups                               12 # of pounds                            700 # of inspections                      ...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT