Budgeted machine-hours 250,000
Actual manufacturing overhead costs $7,300,000
Actual machine-hours 245,000
The company uses normal costing. Its job-costing system has a single manufacturing overhead cost pool. Costs are allocated to jobs using a budgeted machine-hour rate.
1. Compute the budgeted manufacturing overhead rate. (1pt)
2. Compute the amount of under- or overallocation of manufacturing overhead. Prepare a journal entry to dispose of this amount. (1pt)
Mathematical |
Financial |
|
Annual production in units |
50,000 |
100,000 |
Direct material costs |
$150,000 |
$300,000 |
Direct manufacturing labor costs |
$ 50,000 |
$100,000 |
Direct manufacturing labor-hours |
2,500 |
5,000 |
Machine-hours |
25,000 |
50,000 |
Number of production runs |
50 |
50 |
Inspection hours |
1,000 |
500 |
Total manufacturing overhead costs are as follows:
Total Machining costs $375,000
Setup costs $120,000
Inspection costs $105,000
1. Choose a cost driver for each overhead cost pool and calculate the manufacturing overhead cost per unit for each product. (1.5 pt)
2. Compute the manufacturing cost per unit for each product using Activity-based Costing.(2 pts)
Safety considerations require that they each work no more than 40 hours per week. The first chain-saw sharpening and repair required 7 hours of work, and an 80 percent learning curve is anticipated.
Week Units Cumulative Units
October 2–6 8 8
October 9–13 19 27
October 16–20 10 37
October 23–27 27 64
a. How many total hours are required to complete 64 chain saws?(0.5pt)
b. How many hours of work are required for the week ending on Friday the 13th? (1pt)
c. Will Freddie and Jason be able to keep their same week service promise during their busiest week just before Halloween?(2pts)
Get Answers For Free
Most questions answered within 1 hours.