Question

For many years, long-term contracts that qualified for recognition over time were accounted for using an...

For many years, long-term contracts that qualified for recognition over time were accounted for using an approach called the ________ method, and those that did not qualify for recognition over time used a method called _________.

percentage-of-completion; completed contract

completed contract; percentage-of-completion

billings in progress; deferred recognition

Homework Answers

Answer #1

Answer:

Percentage of completion; Completed contract.

Explanation:

For many years, long-term contracts that qualified for recognition over time were accounted for using an approach called the Percentage of completion method, and those that did not qualify for recognition over time used a method called completed contract.

Percentage of completion method are those in which Revenue is recognised as per percentage of completion of contract. For example if contract price is $100000 and contract period is 3 years then Revenue will be recorded all 3 years as per percentage of completion.

Under completed contract method Revenue is Recognised as when contract is completed.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two accounting students were discussing the timing of revenue recognition for long-term construction contracts. The discussion...
Two accounting students were discussing the timing of revenue recognition for long-term construction contracts. The discussion focused on which method was most like the typical revenue recognition method of recognizing revenue at the point of product delivery. Bill argued that recognizing revenue upon project completion was preferable because it was analogous to recognizing revenue at the point of delivery. John disagreed and supported recognizing revenue over time, stating that it was analogous to accruing revenue as a performance obligation was...
roblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
roblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,550,000 $ 4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during...
Dream Home Inc., a real estate developing company, was accounting for its long-term contracts using the...
Dream Home Inc., a real estate developing company, was accounting for its long-term contracts using the completed contract method prior to 2018. At the beginning of 2018, it changed to the percentage-of-completion method. The company decided to use the same for income tax purposes. The tax rate enacted is 40%. Income before taxes under both the methods for the past three years appears below.                                                                2016               2017               2018   Completed contract                         $650,000       $375,000       $350,000 Percentage-of-completion              825,000      ...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long began work on a $400 million fixed-fee construction contract, which was completed in 2024. Cost incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Cost Incurred Estimated Costs to Complete as of December 31 2021 $60 $240 2022 $84 $176 For the year 2022, Long should have recognized gross profit on this contract...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following data pertain to the first two years that the contract was in process. 2020                              2021               Costs incurred to date                                    $   570,000                  $1,557,500    Estimated costs to complete as of 12/31       1,330,000                         667,500 Billings to date                                                     650,000                     1,250,000    Cash collections to date                                     600,000                     1,150,000 1. Using the percentage-of-completion method: A. Compute gross profit to be reported in each...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood began work on a $4,300,000 fixed-fee construction contract, which was completed in 2024. Cost Incurred Estimated Additional Cost to Complete 2021 $800,000 $3,200,000 2022 $1,000,000 $2,200,000 2023 $936,000 $1,064,000 For the year 2023, Redwood should have recognized gross profit on this contract of: A)500,000 B)300,000 C)225,00 D)135,000
The board of directors of Ogle Construction Company is meeting to choose between the completed contract...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018. 2. Construction activities for the year ended December 31, 2018, were...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT