Question

BLC has the following information with respect to variable manufacturing overhead for the month of June....

BLC has the following information with respect to variable manufacturing overhead for the month of June. The budget calls for 10,000 units to be produced using a total of 15,000 machine-hours. The variable overhead costs for the period are budgeted to be $180,000. During June, the actual output was 9,000 units. The total variable overhead costs were $171,000, and 14,000 machine-hours were actually used. BLC uses machine-hours to drive variable overhead.
What is the variable overhead spending variance for the month of June?

A. $3,000 favorable

B. $3,000 unfavorable

C. $9,000 favorable

D. $9,000 unfavorable

Homework Answers

Answer #1

Variable overhead spending variance = Standard vaariable cost-Actual variable cost

                                                              = (15000/10000*9000*12) -171000

Variable overhead spending variance = 9000 U

So answer is d) $9000 Unfavorable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead costs are applied to products on the basis of machine hours. The denominator volume of machine hours is 9,000. Standard Quantity or Hours per unit Standard Price or Rate per unit Standard Cost per unit Direct Materials 3 feet $6 per foot $18 Direct Labor 1.5 direct labor hours $10 per direct labor hour $15 Variable Overhead 2 machine hours $12 per machine hour...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead cost to outputs: Actual total overhead cost incurred $ 24,000 Actual fixed overhead cost incurred $ 10,000 Budgeted fixed overhead cost $ 11,000 Actual machine hours 5,000 Standard machine hours allowed for the units manufactured 4,800 Denominator level — machine hours 5,500 Standard variable overhead rate per machine hour $ 3.00 What is variable overhead spending variance? Group of answer choices $960 favorable $1,000...
Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual...
Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below: Original Budget Actual Costs Variable overhead costs: Supplies $ 6,400 $ 6,590 Indirect labor 10,580 9,930 Fixed overhead costs: Supervision 14,210 14,350 Utilities 13,500 13,550 Factory depreciation 57,440 57,250 Total overhead cost $ 102,130 $ 101,670 The company based its original budget on 6,500 machine-hours. The company actually worked 6,460 machine-hours during the month. The...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,100 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
5.          A company’s manufacturing plans were as follows: Units to be manufactured:       1,000 units Budgeted variable...
5.          A company’s manufacturing plans were as follows: Units to be manufactured:       1,000 units Budgeted variable costs:                      $50,000 [50q ($50 per unit)] Budgeted fixed costs:              $30,000 Budgeted mixed costs:             $20,000 [14,000 + 6q ($14,000 fixed + $6 per unit)] Later, the company actually produced 1,200 units, and incurred variable costs of $52,000; fixed costs of $31,000; and mixed costs of $21,000. The flexible budget for 1,200 units will show the total budgeted cost of $_______. The amount of the overall...
Variable Overhead Spending and Efficiency Variances, Columnar and Formula Approaches Rath Company provided the following information:...
Variable Overhead Spending and Efficiency Variances, Columnar and Formula Approaches Rath Company provided the following information: Standard variable overhead rate (SVOR) per direct labor hour $3.75 Actual variable overhead costs $222,816 Actual direct labor hours worked (AH) 57,200 Actual production in units 15,000 Standard hours (SH) allowed for actual units produced 60,000 Required: 1. Using the columnar approach, calculate the variable overhead spending and efficiency variances. Enter amounts as positive numbers. (1) (2) (3)                   Spending Efficiency...
Xcel Technologies, Inc. applies variable manufacturing overhead to products based on machine hours. The standard variable...
Xcel Technologies, Inc. applies variable manufacturing overhead to products based on machine hours. The standard variable overhead rate is $5 per machine hour. The standard time allowed for producing one unit is 2 machine hours. During the month of August, the company produced 500 units. It incurred actual variable costs of $5,655 and used 870 machine hours. Calculate the variable overhead efficiency variance for the month of August. A) $650 favorable B) $650 unfavorable C) $845 favorable D) $845 unfavorable
Pratt, Inc., uses a standard costing system and develops its predetermined overhead rate from the annual...
Pratt, Inc., uses a standard costing system and develops its predetermined overhead rate from the annual flexible budget. The budget is based on an expected annual output of 40,000 units requiring total 160,000 budgeted direct labor hours. The company applied overhead based on direct labor hours. Annual budgeted overhead costs totaal $1,280,000of which $480,000 is variable overhead. A total of 30,000 units were produced during the year, using 100,000direct labor hours. Actual overhead costs incurred for the year were total...
A company has prepared a master budget for the month of February when they expected to...
A company has prepared a master budget for the month of February when they expected to sell 4,000 units. They actually sold 3,750 units. Calculate the flexible budget and the spending and volume variances for February. Identify if the variances are favorable or unfavorable. Actual Costs 3,750 Units Spending Variances Flexible Budget _______Units Volume Variances Master Budget 4,000 Units Manufacturing Costs: Direct Materials $14,500 $16,000 Direct Labor 38,500 40,000 Variable Manufacturing Overhead 12,000 14,000 Fixed Manufacturing Overhead 20,000 21,000 Total...
The following information relating to a company's overhead costs is available. Budgeted fixed overhead rate per...
The following information relating to a company's overhead costs is available. Budgeted fixed overhead rate per machine hour $ 0.50 Actual variable overhead $ 73,000 Budgeted variable overhead rate per machine hour $ 2.50 Actual fixed overhead $ 17,000 Budgeted hours allowed for actual output achieved 32,000 Based on this information, the total overhead variance is: Multiple Choice $6,000 favorable. $1,000 favorable. $7,000 favorable. $6,000 unfavorable. $1,000 unfavorable.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT