Standard Product Cost
Sana Rosa Company manufactures unfinished home furniture. Sana Rosa uses a standard cost system. The direct labor, direct materials, and factory overhead standards for an unfinished dining room table are as follows:
Direct labor: | standard rate | $18.00 per hr. |
standard time per unit | 2 hrs. | |
Direct materials (oak): | standard price | $8.50 per bd. ft. |
standard quantity | 18 bd. ft. | |
Variable factory overhead: | standard rate | $2.80 per direct labor hr. |
Fixed factory overhead: | standard rate | $1.20 per direct labor hr. |
a. Determine the standard cost per dining room
table. If required, round your answer to two decimal places.
$per table
b. A standard cost system provides Sana Rosa management a cost control tool using the principle of . Using this principle, cost deviations from standards can be investigated and corrected.
a. Determine the standard cost per dining room table
particular |
Amount $ |
Direct labor Per unit (18x2) |
36 |
Direct Material Per unit (8.50x18) |
153 |
variable Factory Overhead per unit (2.8*2) |
5.6 |
Fixed Factory Overhead per unit (1.20*2) |
2.4 |
Standard cost per Dinning room table |
197 |
b.
A standard cost system provides Sana Rosa management a cost control tool using the principle of Cost control. Using this principle, Major cost deviations from standards can be investigated and corrected.