Part 4. Questions 6,7. [ Use Video-1 under Scheduling heading. ]
[Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.]
The jobs A,B,C,D,E, arrived in that order to be processed on two machines.
Job |
A |
B |
C |
D |
E |
Time on Machine 1 |
45 |
53 |
63 |
31 |
75 |
Time on Machine 2 |
42 |
65 |
61 |
53 |
77 |
Question 6. Which is the Johnson’s Rule schedule? (A) ‘ACEBD’ (B) ‘DCABE’ (C) ‘DBECA’ (D) ‘DABEC’ (E) none of the above |
Question 7. Consider the FIFO schedule of (A,B,C,D,E). How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The total time of completion is 344 Statement 2. The flow time of job D is 245 Statement 3. The total queue time of job C is 100 Statement 4. The total idle time of machine 2 is 45 . . . |
Question 6
Shortest processing time (time) |
Job |
Operation (1 Or 2) |
Sequence |
31 |
D |
Operation 1 |
First |
42 |
A |
Operation 2 |
Last |
53 |
B |
Operation 1 |
Second |
61 |
C |
Operation 2 |
Second last |
75 |
E |
Operation 1 |
Third |
Now the sequence is D-B-E-C-A
Option (C)
.
Question 7
Job | Start Hour | End Hour | Idle Time | Start Hour | End Hour | Idle Time |
A | 0 | 45 | 0 | 45 | 87 | 45 |
B | 45 | 98 | 0 | 98 | 163 | 11 |
C | 98 | 161 | 0 | 163 | 224 | 0 |
D | 161 | 192 | 0 | 224 | 277 | 0 |
E | 192 | 267 | 0 | 277 | 354 | 0 |
Total | 0 |
Statement 1. The total time of completion is 344
Statement 2. The flow time of job D is 245
Statement 3. The total queue time of job C is 100
Statement 4. The total idle time of machine 2 is 45
All statements are false
Option (A)
Get Answers For Free