Question

Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs...

Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ]

[Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.]

The jobs A,B,C,D,E, arrived in that order to be processed on two machines.

Job

A

B

C

D

E

Time on Machine 1

45

53

63

31

75

Time on Machine 2

42

65

61

53

77

Question 6. Which is the Johnson’s Rule schedule?

     (A) ‘ACEBD’     (B) ‘DCABE’     (C) ‘DBECA’     (D) ‘DABEC’   (E) none of the above

Question 7. Consider the FIFO schedule of (A,B,C,D,E).

How many statements are correct?   (A) 0 (B) 1   (C) 2   (D) 3   (E) 4

Statement 1. The total time of completion is 344

Statement 2. The flow time of job D is 245

Statement 3. The total queue time of job C is 100

Statement 4. The total idle time of machine 2 is 45

. . .

Homework Answers

Answer #1

Question 6

Shortest processing time (time)

Job

Operation (1 Or 2)

Sequence

31

D

Operation 1

First

42

A

Operation 2

Last

53

B

Operation 1

Second

61

C

Operation 2

Second last

75

E

Operation 1

Third

Now the sequence is D-B-E-C-A

Option (C)

.

Question 7

Job Start Hour End Hour Idle Time Start Hour End Hour Idle Time
A 0 45 0 45 87 45
B 45 98 0 98 163 11
C 98 161 0 163 224 0
D 161 192 0 224 277 0
E 192 267 0 277 354 0
Total 0

Statement 1. The total time of completion is 344

Statement 2. The flow time of job D is 245

Statement 3. The total queue time of job C is 100

Statement 4. The total idle time of machine 2 is 45

All statements are false

Option (A)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Part 5.   Questions 8,9. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs...
Part 5.   Questions 8,9. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs in a schedule is 1st,2nd,3rd, for A,B,C, respectively.] Consider the jobs scheduled on two machines in the order of (A,B,C) where each job is started as soon as possible. The processing times for each job on each machine are given in the table below. Assume time on machine #1 is represented with “(1)” and on machine #2 with “(2)”. Job Machine#1 Time Machine#2 Time...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
[Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.] The jobs A,B,C,D,E,...
[Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.] The jobs A,B,C,D,E, arrived in that order to be processed on two machines. Job A B C D E Time on Machine 1 40 48 58 26 70 Time on Machine 2 37 60 56 48 72 Question 6. Which is the Johnson’s Rule schedule?      (A) ‘DBECA’     (B) ‘ACEBD’     (C) ‘DCABE’     (D) ‘DABEC’   (E) none of the above Question 7. Consider the FIFO schedule of (A,B,C,D,E)....
You are given the independent jobs A(5), B(7), C(10), D(12), E(6), F(4), G(3). (a) Using the...
You are given the independent jobs A(5), B(7), C(10), D(12), E(6), F(4), G(3). (a) Using the alphabetical order priority list above, if the jobs are scheduled on 3 processors, what is the completion time? (b) If the decreasing time algorithm is used to schedule the jobs on 3 processors, what is the completion time? (c) If the decreasing time algorithm is used to schedule the jobs on 3 processors, which is the second job scheduled on processor 1? A B...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,170. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,030 $3,160 102 3,700 4,270 103 2,450 2,090 104 8,300 7,840 105 5,270 5,970 106 3,850 3,790 For general factory use 1,030 4,680 Factory overhead costs incurred on account, $5,790....
You are given the independent jobs A(5), B(7), C(10), D(12), E(6), F(4), G(3). (a) Using the...
You are given the independent jobs A(5), B(7), C(10), D(12), E(6), F(4), G(3). (a) Using the alphabetical order priority list above, if the jobs are scheduled on 3 processors, what is the completion time? (b) If the decreasing time algorithm is used to schedule the jobs on 3 processors, what is the completion time? 21 Incorrect: Your answer is incorrect. (c) If the decreasing time algorithm is used to schedule the jobs on 3 processors, which is the second job...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Processing Due Job Time (days) Date (Days) W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A. 0 B. 1 C. 2 D. 3 E. 4
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job A, Process time =14 days, and due date November 26 Job B, Process time= 11 days, and due date = November 25 Job C, Process time =7 days, and due date= December 14 Job D, Process time=6 days, and due date= November 29 Job E, Process time= 2 days, and due date= November 20 Schedule the jobs according to SPT. What are the average...
Tybee Industries Inc. uses a job order cost system A type of cost accounting system that...
Tybee Industries Inc. uses a job order cost system A type of cost accounting system that provides for a separate record of the cost of each particular quantity of product that passes through the factory. . The following data summarize the operations related to production for January, the first month of operations: a. Materials purchased on account, $28,790. b. Materials requisitioned The form or electronic transmission used by a manufacturing department to authorize materials issuances from the storeroom. and factory...
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule. Job Due Date Remaining Time (Days) A 212 6 B 209 3 C 214 10 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum lateness?