Luthan Company uses a plantwide predetermined overhead rate of $22.70 per direct labor-hour. This predetermined rate...

Luthan Company uses a plantwide predetermined overhead rate of $22.70 per direct labor-hour. This predetermined rate was based on a cost formula that estimated $272,400 of total manufacturing overhead cost for an estimated activity level of 12,000 direct labor-hours.

The company incurred actual total manufacturing overhead cost of $268,000 and 10,700 total direct labor-hours during the period.

Required:

Determine the amount of manufacturing overhead cost that would have been applied to all jobs during the period.

Homework Answers

Answer #1

Answer :-

Manufacturing overhead cost that applied to all jobs = Predetermined overhead Rate × Actual Direct labor hours incurred during the period

Predetermined Overhead Rate = $22.70 per direct labor hours

Actual Direct labor hours incurred during the period = 10,700 direct labor hours during the period.

Manufacturing overhead cost that applied to all jobs = $22.70 per direct labor hours × 10,700 direct labor hours

Manufacturing overhead cost that applied to all jobs = $242,890

The amount of manufacturing overhead cost that would have been applied to all jobs during the period is $242,890 .

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
5. Assume (1) a company’s plantwide predetermined overhead rate is $13.00 per direct labor-hour, and (2)...
5. Assume (1) a company’s plantwide predetermined overhead rate is $13.00 per direct labor-hour, and (2) its job cost sheet for Job X shows that this job incurred direct materials and direct labor charges of $500 and $360, respectively. If Job X’s total job cost is $1,289, how many direct labor-hours were worked on this job? 6. Assume (1) actual machine-hours worked during the period of 54,000 hours, (2) estimated machine-hours to be worked during the period of 55,600 hours,...
Osborn Manufacturing uses a predetermined overhead rate of $19.70 per direct labor-hour. This predetermined rate was...
Osborn Manufacturing uses a predetermined overhead rate of $19.70 per direct labor-hour. This predetermined rate was based on a cost formula that estimates $265,950 of total manufacturing overhead for an estimated activity level of 13,500 direct labor-hours. The company incurred actual total manufacturing overhead costs of $260,000 and 13,000 total direct labor-hours during the period. Required: 1. Determine the amount of underapplied or overapplied manufacturing overhead for the period. 2. Assuming that the entire amount of the underapplied or overapplied...
Osborn Manufacturing uses a predetermined overhead rate of $18.90 per direct labor-hour. This predetermined rate was...
Osborn Manufacturing uses a predetermined overhead rate of $18.90 per direct labor-hour. This predetermined rate was based on a cost formula that estimates $240,030 of total manufacturing overhead for an estimated activity level of 12,700 direct labor-hours. The company actually incurred $237,000 of manufacturing overhead and 12,200 direct labor-hours during the period. Required: 1. Determine the amount of underapplied or overapplied manufacturing overhead for the period. 2. Assume that the company's underapplied or overapplied overhead is closed to Cost of...
A company uses a predetermined overhead rate based on direct labor costs to apply manufacturing overhead...
A company uses a predetermined overhead rate based on direct labor costs to apply manufacturing overhead to jobs. At the beginning of the year the company estimated its total manufacturing overhead cost at $350,000 and its direct labor costs at $200,000. The actual overhead cost incurred during the year was $362,000 and the actual direct labor costs incurred on jobs during the year was $208,000. The manufacturing overhead for the year would be: A) $12,000 underapplied B) $12,000 overapplied C)...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...
Your company computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At...
Your company computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 20,000 direct labor-hours would be required for the period's estimated level of production. The company also estimated $94,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $2.00 per direct labor-hour. Your company's actual manufacturing overhead cost for the year was $123,900 and its actual total direct labor was 21,000 hours....
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At...
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 39,000 direct labor-hours would be required for the period’s estimated level of production. The company also estimated $503,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $3.00 per direct labor-hour. Harris’s actual manufacturing overhead cost for the year was $691,149 and its actual total direct labor was 39,500 hours. Required:...
2. Sigma Corporation estimates its plantwide predetermined overhead rate annually on the basis of direct labor-hours....
2. Sigma Corporation estimates its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 34,000 direct labor-hours would be required for the period’s estimated level of production. The company also estimated $559,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $4.00 per direct labor-hour. Sigma’s actual manufacturing overhead cost for the year was $758,696 and its actual total direct labor was 34,500 hours....
Your Company uses a predetermined overhead rate based on direct labor cost. The POR is 80%...
Your Company uses a predetermined overhead rate based on direct labor cost. The POR is 80% of direct labor costs. Use the following information to determine by how much the manufacturing overhead cost for the current year will be over or under applied.                     Direct labor-hours: Estimated for the year................ 24,000 Actual hours worked.................. 19,500 Direct labor cost: Estimated for the year................ $300,000 Actual cost incurred................... $210,000 Manufacturing overhead: Estimated for the year................ $240,000 Actual cost incurred................... $185,000 The manufacturing overhead...
Exercise 2-1 Compute a Predetermined Overhead Rate [LO2-1] Harris Fabrics computes its plantwide predetermined overhead rate...
Exercise 2-1 Compute a Predetermined Overhead Rate [LO2-1] Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 35,000 direct labor-hours would be required for the period’s estimated level of production. The company also estimated $555,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $2.00 per direct labor-hour. Harris’s actual manufacturing overhead cost for the year was $692,504 and its...