Question

Shannon Company acquires land with a shed on it to use as a plant site for...

Shannon Company acquires land with a shed on it to use as a plant site for $56,000. Additional information is as follows:

Removal of shed                                                  $     300

Filling and Grading 1,500

Proceeds from selling shed lumber 120

Broker commission 1,130

Paving of parking lot 10,000

Closing costs 560

Shannon will record the acquisition cost of the land as

Homework Answers

Answer #1

Cost of Land = $59,370

($56,000 + 1,500 + 1,130 + 560 + 300 – 120)

I hope my workings are enough to understand                       
Thanks in advance for giving me positive ratings                      
for any clarification feel free to comment on it                       
May God bless you and have a wonderful day                      

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Angus Corp. acquires land for $105,000 cash. Additional costs are as follows: Removal of shed $...
Angus Corp. acquires land for $105,000 cash. Additional costs are as follows: Removal of shed $ 500 Filling and grading 3,200 Residual value of lumber from shed 150 Paving of parking lot 16,000 Closing costs 1,350 Angus will record the cost of the land as
Chapter 10 Acquisition and Disposition of Property, Plant and Equipment On July 1, 2018, Forward Corporation...
Chapter 10 Acquisition and Disposition of Property, Plant and Equipment On July 1, 2018, Forward Corporation purchased a parcel of land as a factory site for $185,000. An old building on the property was demolished and construction began on a new warehouse that was completed on October 15, 2018. Costs incurred on the construction project are listed below.                Cost of building construction…………………………………          $620,000                Title insurance…………………………………………………               1,500                Cost of constructing a driveway……………………………….               8,000                Legal fees to purchase...
The following payments and receipts are related to land, land improvements, and buildings acquired for use...
The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk next to the item letter. a. Fee paid to attorney for title search $ 2,395 b. Cost of real estate acquired as a plant site: Land 283,200 Cost of real estate acquired as a plant site: Building 57,400 c. Delinquent real estate taxes on property, assumed by purchaser 15,175 d. Cost of...
Question 5 A plant site donated by a township to a manufacturer that plans to open...
Question 5 A plant site donated by a township to a manufacturer that plans to open a new factory should be recorded on the manufacturer's books at ___________. Question 5 options: A. the nominal cost of taking title to it i B. Its fair value C. one dollar (since the site cost nothing but should be included in the balance sheet) D. the value assigned to it by the company's directors Question 6 Which of the following costs are capitalized...