Required information
[The following information applies to the questions
displayed below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,580,000 | $ | 3,830,000 | $ | 3,230,000 | |||
Estimated costs to complete as of year-end | 6,020,000 | 3,130,000 | 0 | ||||||
Calculation of Revenue and Gross Profit :-
Particulars | 2018 | 2019 | 2020 |
Cost Incurred Each Year (a) | 2580000 | 4042000 | 2175800 |
Cost Incurred to Date (b) | 2580000 | 6622000 | 8797800 |
Estimated Costs (c) | 6020000 | 1978000 | |
Total Estimated Costs (d) = (b+c) | 8600000 | 8600000 | 8797800 |
% Completed (e) = (b/d)*100 | 30% | 77% | 100% |
Revenue (f) ($10000000*e)-Last year Revenue | 3000000 | 4700000 | 2300000 |
Expenses (g) | 2580000 | 4042000 | 2175800 |
Gross Profit (h) = (f-g) | 420000 | 658000 | 124200 |