Decision making #3-Use of Limited Resources-Singe Constraint | |||||||||||||||||||||||||
Bush Manufacturing has the following labor hours available for producing M and N: | 25,000 | Total Direct labor hours available | |||||||||||||||||||||||
Consider the following information: | |||||||||||||||||||||||||
M | N | Total | |||||||||||||||||||||||
Required Labor per unit in hours | 2 | 3 | |||||||||||||||||||||||
Maximum demand in units | 8,000 | 7,000 | |||||||||||||||||||||||
Contribution Margin per unit | 8 |
9
|
What is the optimal product mix(how many M and N should be produced)? Explain your answer and show computations.
Product M | Product N | |
Contribution margin per unit | 8 | 9 |
Labour hour per unit | 2 | 3 |
Contribution margin per labour hour | 4 | 3 |
Rank | 2 | 1 |
Calculate optimal product Mix :
Unit | Labour hour | |
Product N (7000*3) | 7000 | 21000 |
Product M (25000-21000)/2 | 2000 | 4000 |
Optimal product Mix is 7000 Unit of product N and 2000 Unit of product M