Physical Flow Schedule Nelrok Company manufactures fertilizer. Department 1 mixes the chemicals required for the fertilizer. The following data are for the year: BWIP (40% complete) 40,000 Units started 142,500 Units in EWIP (60% complete) 35,000 Required: Prepare a physical flow schedule. Nelrok Company Physical Flow Schedule Units to account for: Units in beginning work in process Units started 142,500 Total units to account for Units accounted for: Completed from beginning work in process Started and completed Units in ending work in process Total units accounted for
solution
given data
given that Physical Flow Schedule Nelrok Company manufactures fertilizer. Department 1 mixes the chemicals required for the fertilizer.
The BWIP (40% complete) 40,000 Units started 142,500 Units in EWIP (60% complete) 35,000 Required: Prepare a physical flow schedule. Nelrok Company Physical Flow Schedule Units to account for: Units in beginning work in process Units started 142,500
nerlock company | |
units to account for: | whole units |
opening work in progress | 25000 |
started | 142500 |
total units to account for | 167500 |
oping work in progress | 25000 |
started and completed | 107500 |
closing work in progress | 35000 |
total units accounted for | 167500 |