The controller established the following overhead cost pools and cost drivers:
Overhead Cost Pool |
Budgeted Overhead |
Cost Driver |
Estimated Cost Driver Level |
Machine setups |
$207,000 |
# of setups |
180 setups |
Material handling |
138,000 |
# of pounds |
12,000 |
Quality control |
245,000 |
# of inspections |
1,000 inspections |
Other overhead cost |
220,000 |
# of machine hrs |
20,000 machine hrs |
An order of steel tubing used the following amounts of the cost drivers:
# of setups 12
# of pounds 700
# of inspections 20
# of machine hours 900
Answer and Show Work:
Overhead assigned to the order using MH: |
Overhead assigned to the order using ABC: |
1) | overhead assinged to the order using MH | |||||||
810,000/20,000*900 | ||||||||
36450 | answer | |||||||
2) | Activity rates | |||||||
A | B | c=a/b | D | E=c*d | ||||
oh | level | rate | used | allocated | ||||
machine setups | 207,000 | 180 | 1150 | 12 | 13800 | |||
material handling | 138,000 | 12000 | 11.5 | 700 | 8050 | |||
quality control | 245,000 | 1000 | 245 | 20 | 4900 | |||
other overhead cost | 220,000 | 20,000 | 11 | 900 | 9900 | |||
total | 810,000 | 36650 | ||||||
36,650 | answer |