Pinnacle Inc. manufactures curtains to client specifications. It has two cost categories that are directly traced to its products: materials and labor. It also has estimated overhead that consists of:
Pinnacle is trying to calculate the cost of making Job #454, which includes:
The company also expects to use 21,055 labor hours for the year. If Pinnacle allocates overhead based on $250,000 estimated direct labor dollars, what is the total cost ofJob #454? *Hint, make a job order cost sheet for Job 454. It should include materials, labor, and overhead. Round each step to the nearest 2 decimal places. For your final answer, round to the nearest dollar.
Computation of Total cost of Job #454:
Total cost = Material + Labor + Overhead
= $10875 + (23 hours x $12) + ($21055 hours x $2.23)
= $10875 + $276 + $46952.65
= $58103.65 i.e. $58104.
Workings:
Overhead cost per Direct labor hour = Total Estimated overhead cost / Total Estimated Direct labor cost
Total Estimated overhead cost = $197106 + $195451 + $165700 = $558257.
Total Estimated Direct labor cost = $250000
Overhead cost per Direct labor hour = $558257 / $250000 = $2.23