Question

The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...

The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows:

Standard Costs
Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour
Variable overhead 3 hours per unit @ $1.99 per hour

Actual Costs
    Total variable cost, $17,900
    Total fixed cost, $8,200

The total factory overhead cost variance is

a.$-10 unfavorable

b.$690 unfavorable

c.$1,390 favorable

d.$690 favorable

Homework Answers

Answer #1
Variable overhead controllable variance = ($17,900 - [3,000 units * 3 hours * $1.99 per])
Variable overhead controllable variance = ($17,900 - $17,910)
Variable overhead controllable variance = $10 Favorable
Fixed overhead volume variance = (10,000 hours - [3,000 units * 3 hours per unit] * $0.70 per hour)
Fixed overhead volume variance = (10,000 hours - 9,000 hours) * $0.70 per hour
Fixed overhead volume variance = 1,000 hours * $0.70 per hour
Fixed overhead volume variance = $700 Unfavorable
Total factory overhead cost variance = $10 Favorable + $700 Unfavorable
Total factory overhead cost variance = $690 Unfavorable
Therefore, the correct answer is b) $690 Unfavorable.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour Variable overhead 3 hours per unit @ $2.01 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $7,900 The total factory overhead cost variance is a.$-90 unfavorable b.$610 unfavorable c.$1,310 favorable d.$610 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.75 per hour Variable overhead 3 hours per unit @ $1.97 per hour Actual Costs     Total variable cost, $17,900     Total fixed cost, $8,000 The amount of the total factory overhead cost variance is a.$5,000 favorable b.$5,000 unfavorable c.$3,125 unfavorable d.$6,875 favorable
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.77 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $18,100     Total fixed cost, $8,200 The amount of the variable factory overhead controllable variance is a.$2,056 favorable b.$0 c.$2,056 unfavorable d.$1,645 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.71 per hour Variable overhead 3 hours per unit at $2.06 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,000 The fixed factory overhead volume variance is a.$0 b.$909 unfavorable c.$1,136 unfavorable d.$909 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.78 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $17,800     Total fixed cost, $8,100 The variable factory overhead controllable variance is a.$1,756 favorable b.$1,756 unfavorable c.$1,405 favorable d.$0
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.72 per hour Variable overhead 3 hours per unit at $1.99 per hour Actual Costs Total variable cost, $17,800 Total fixed cost, $7,900 The total factory overhead cost variance is
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.72 per hour Variable overhead 3 hours per unit @ $2.06 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $7,900 The fixed factory overhead volume variance is a.$720 unfavorable b.$0 c.$576 unfavorable d.$576 favorable The following data are given for Bahia Company: Budgeted...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 994 units were actually produced. Labor standards were 7.6 hours per completed unit at a standard rate of $12.86 per hour. The direct labor rate variance is a.$6,881.72 unfavorable b.$6,881.72 favorable c.$5,577.18 unfavorable d.$5,577.18 favorable 21. Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.08 per hour. Original...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 3,000 computers: Actual: Variable factory overhead $122,200 Fixed factory overhead 35,000 Standard: 3,000 hrs. at $49 147,000 If productive capacity of 100% was 5,000 hours and the total factory overhead cost budgeted at the level of 3,000 standard hours was $161,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual...
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.61 Actual Costs Direct materials 2,600 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is $426 favorable $426 unfavorable $1,066 favorable $1,066 unfavorable Q2: The standard costs and actual costs for direct materials for the manufacture of 2,650 actual units of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT