Exercise 7-13 Computing ABC Product Costs [LO7-3, LO7-4]
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production |
||
Hubs | 0.80 | 30,000 | units |
Sprockets | 0.40 | 54,000 | units |
Additional information about the company follows:
Hubs require $23 in direct materials per unit, and Sprockets require $20.
The direct labor wage rate is $10 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 17,595 | 85 | 68 | 153 |
Special processing (machine-hours) | $ | 202,500 | 4,500 | 0 | 4,500 |
General factory (organization-sustaining) | $ | 261,600 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Complete this question by entering your answers in the tabs below.
Required 1
Required 2
Determine the unit product cost of each product according to the ABC system. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
|
1. Compute the activity rate for each activity cost pool.
Activity rate | |
Machine setups (17595/153) | 115 per setup |
Special processing (202500/4500) | 45 per machine hour |
2. Determine the unit product cost of each product according to the ABC system.
Hubs overhead cost per unit = (115*85+202500)/30000 = 7.08
Sprockets = (115*68)/54000 = 0.14
Hubs | Sprockets | |
Direct material | 23 | 20 |
Direct labour | 8 | 4 |
Overhead | 7.08 | 0.14 |
Unit cost | 38.08 | 24.14 |