Question

The difference between budgeted fixed manufacturing overhead and the fixed overhead applied to production is the:...

The difference between budgeted fixed manufacturing overhead and the fixed overhead applied to production is the: Select one: a. sum of the spending and efficiency variances. b. efficiency variance. c. spending variance. d. volume variance. e. controllable variance.

Homework Answers

Answer #1

Answer: Option d. volume variance

The volume variance is the difference between the budgeted fixed overheads and the fixed overheads applied to production.

The sum of the spending and efficiency variances is the total variable overhead variance and hence option a. is incorrect.

Efficiency variance is computed for variable overheads and not fixed overheads hence, option b. is incorrect.

Spending variance for fixed overheads is the difference between the actual overheads and the budgeted overheads hence, option c. is incorrect.

A controllable variance is a variance that is not affected due to change in volumes and hence option e is incorrect.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
True-False ____1. Budgeted overhead cost rates can be expressed as an amount per unit of output...
True-False ____1. Budgeted overhead cost rates can be expressed as an amount per unit of output or per unit of input. ____2. There is no fundamental difference between the budgeted variable-overhead cost rate per unit of input and the budgeted price of individual direct materials. ____3. The variable-overhead spending variance is unfavorable if the actual variable overhead cost rate per unit of input (the cost-allocation base) is greater than the budgeted variable overhead cost rate per unit of input. ____4....
Lihue, Inc., applies fixed overhead at the rate of $4.20 per unit. Budgeted fixed overhead was...
Lihue, Inc., applies fixed overhead at the rate of $4.20 per unit. Budgeted fixed overhead was $1,457,820. This month 342,100 units were produced, and actual overhead was $1,450,000. Required A What are the fixed overhead price and production volume variances for Lihue? (Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.) Fixed overhead price variance    Fixed overhead production volume variance Required B: What...
Lihue, Inc., applies fixed overhead at the rate of $4.00 per unit. Budgeted fixed overhead was...
Lihue, Inc., applies fixed overhead at the rate of $4.00 per unit. Budgeted fixed overhead was $1,393,200. This month 342,300 units were produced, and actual overhead was $1,380,000. Required: What are the fixed overhead price and production volume variances for Lihue? fixed overhead price variance fixed overhead production volume variance b. What was budgeted production for the month?
Assume that $102,000 is budgeted for fixed overhead. $95,000 was actually spent on fixed overhead. Fixed...
Assume that $102,000 is budgeted for fixed overhead. $95,000 was actually spent on fixed overhead. Fixed overhead is applied to production at $10 per labor hour, and the achieved output was 5,000 units. The standard labor hours are 2 hours per unit. The total fixed overhead variance is $2,000 favorable. All of these choices are correct. The fixed overhead spending variance is $7,000 favorable. The fixed overhead volume variance is $5,000 unfavorable.
The difference between the actual variable factory overhead costs and the budgeted variable overhead for actual...
The difference between the actual variable factory overhead costs and the budgeted variable overhead for actual production is termed variable factory overhead controllable variance. True False
Citi Company uses a standard cost system in which manufacturing overhead is applied to units of...
Citi Company uses a standard cost system in which manufacturing overhead is applied to units of product on the basis of standard machine-hours. During February, the company used a denominator activity of 60,000 machine-hours in computing its predetermined overhead rate. However, 75,000 standard machine-hours were allowed for the month's actual production. If the fixed manufacturing overhead volume variance for February was $6,800 unfavorable, then the total budgeted fixed manufacturing overhead cost for the month was (closest to ) Select one:...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)   ...
The information shown below was taken from the annual manufacturing overhead cost budget of Sarasota Company....
The information shown below was taken from the annual manufacturing overhead cost budget of Sarasota Company. Variable manufacturing overhead costs $66,700 Fixed manufacturing overhead costs $23,000 Normal production level in labor hours 23,000 Normal production level in units 4,600 Standard labor hours per unit 5 During the year, 4,500 units were produced, 17,100 hours were worked, and the actual manufacturing overhead was $89,250. Actual fixed manufacturing overhead costs equaled budgeted fixed manufacturing overhead costs. Overhead is applied on the basis...
Lihue, Inc., applies fixed overhead at the rate of $3.20 per unit. Budgeted fixed overhead was...
Lihue, Inc., applies fixed overhead at the rate of $3.20 per unit. Budgeted fixed overhead was $1,129,920. This month 343,100 units were produced, and actual overhead was $1,110,000. Required: a. What are the fixed overhead price and production volume variances for Lihue? (Indicate the effect of each variance by "F" for favorable, or "U" for unfavorable.) b. What was budgeted production for the month? (Do not round intermediate calculations.)
Assume the following: Actual Variable Overhead $17,000 Allocated Variable Overhead $18,000 Budgeted Variable Overhead $17,500 VOH...
Assume the following: Actual Variable Overhead $17,000 Allocated Variable Overhead $18,000 Budgeted Variable Overhead $17,500 VOH Spending Variance Variance $1500 F VOH Efficiency Variance $500 U Prepare the following journal entries: a. Record Actual Overhead b. Record Allocated Overhead c. Record the variances and close the overhead accounts d. Close the variance accounts Answer the following questions: e. Is overhead under or over-applied? f. Did you increase or decrease COGS in entry (d)? Why does this make sense?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT