Cost Information
During October, McCourt Associates incurred total production costs of $85,500 for copyediting manuscripts and had the following equivalent units schedule:
Units completed | 285 |
Units in EWIP × Fraction complete: 25 × 0.6 | 15 |
Equivalent units | 300 |
Required:
1. Calculate the cost of copyediting one
manuscript for October.
$ per manuscript
2. Assign costs to manuscripts completed and to EWIP and then do a cost reconciliation.
Manuscripts completed | $ |
EWIP | |
Total assigned | $ |
3. What if the costs
assigned to units completed and EWIP total were calculated using a
unit cost of $310? Calculate the total costs assigned.
$
What is the discrepancy between the costs assigned and the costs
to account for?
$
1) Cost of one manuscript = 85500/300 = 285 per manuscript
2)
Manuscripts completed (285*285) | 81225 |
EWIP (285*15) | 4275 |
Total Assigned | 85500 |
3. What if the costs assigned to units completed and EWIP total were calculated using a unit cost of $310? Calculate the total costs assigned.
Manuscripts completed = 285*310 = 88350
EWIP = 310*15 = 4650
Total Cost assigned = (285*310)+(310*15) = 93000
4) What is the discrepancy between the costs assigned and the costs to account for?
93000-85500 = 7500