Stillwater Designs rebuilds defective units of its S12L7 Kicker speaker model. During the year, Stillwater rebuilt 8,500 units. Materials and labor standards for performing the repairs are as follows:

Direct materials (1 recon kit @ $160) $160
Direct materials (1 cabinet @ $80) 80
Direct labor (3 hrs. @ $11) 33

Required:

1. Compute the standard hours allowed for a volume of 8,500 rebuilt units.
hours

2. Compute the standard number of kits and cabinets allowed for a volume of 8,500 rebuilt units.

Standard number of kits: kits
Standard number of cabinets: cabinets

3. Suppose that during the first month of the year, 3,550 standard hours were allowed for the units rebuilt. How many units were rebuilt during the first month? Round your answer to the nearest whole unit.
units

Standard Quantities of Labor and Materials

Stillwater Designs rebuilds defective units of its S12L7 Kicker speaker model. During the year, Stillwater rebuilt 8,500 units. Materials and labor standards for performing the repairs are as follows:

Direct materials (1 recon kit @ $160) $160
Direct materials (1 cabinet @ $80) 80
Direct labor (3 hrs. @ $11) 33

Required:

1. Compute the standard hours allowed for a volume of 8,500 rebuilt units.
hours

2. Compute the standard number of kits and cabinets allowed for a volume of 8,500 rebuilt units.

Standard number of kits: kits
Standard number of cabinets: cabinets

3. Suppose that during the first month of the year, 3,550 standard hours were allowed for the units rebuilt. How many units were rebuilt during the first month? Round your answer to the nearest whole unit.
units

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Stillwater Designs rebuilds defective units of its S12L7 Kicker speaker model. During the year, Stillwater rebuilt...
Stillwater Designs rebuilds defective units of its S12L7 Kicker speaker model. During the year, Stillwater rebuilt 9,000 units. Materials and labor standards for performing the repairs are as follows: Direct materials (1 recon kit @ $160) $160 Direct materials (1 cabinet @ $20) 20 Direct labor (3 hrs. @ $12) 36 1. Compute the standard hours allowed for a volume of 9,000 rebuilt units. hours 2. Compute the standard number of kits and cabinets allowed for a volume of 9,000...
Problem 10-11 (Algo) Direct Materials and Direct Labor Variances; Computations from Incomplete Data [LO10-1, LO10-2] Sharp...
Problem 10-11 (Algo) Direct Materials and Direct Labor Variances; Computations from Incomplete Data [LO10-1, LO10-2] Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $49,170, all of which were used in the production of 2,750 units of...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $45,210, all of which were used in the production of 2,500 units of product. In addition, 4,100 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $42,660, all of which were used in the production of 2,250 units of product. In addition, 4,600 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $52,740, all of which were used in the production of 2,750 units of product. In addition, 4,500 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $52,965, all of which were used in the production of 2,920 units of product. In addition, 4,500 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $42,660, all of which were used in the production of 2,250 units of product. In addition, 4,600 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $64,440, all of which were used in the production of 3,500 units of product. In addition, 5,000 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 11 per foot $ 33 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $111,300, all of which were used in the production of 3,200 units of product. In addition, 4,900 direct labor-hours were worked on the product during the month. The...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...
Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $54,285, all of which were used in the production of 3,200 units of product. In addition, 4,900 direct labor-hours were worked on the product during the month. The...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT