Question

Dwight Donovan, the president of Vernon Enterprises, is considering two investment opportunities. Because of limited resources,...

Dwight Donovan, the president of Vernon Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of four years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $115,000 and for Project B are $49,000. The annual expected cash inflows are $35,497 for Project A and $16,817 for Project B. Both investments are expected to provide cash flow benefits for the next four years. Vernon Enterprises’ desired rate of return is 8 percent. (PV of $1 and PVA of $1) (Use appropriate factor(s) from the tables provided.)

Required

  1. Compute the net present value of each project. Which project should be adopted based on the net present value approach?

  2. Compute the approximate internal rate of return of each project. Which one should be adopted based on the internal rate of return approach?

Compute the net present value of each project. Which project should be adopted based on the net present value approach? (Round your final answers to 2 decimal places.)

Net Present Value
Project A
Project B
Which project should be adopted?

Compute the approximate internal rate of return of each project. Which one should be adopted based on the internal rate of return approach?

Internal Rate of Return
Project A %
Project B %
Which project should be adopted?

Homework Answers

Answer #1
a) NPV = Present value of inflows - PV of outflows
Project A = [$ 35497 x PVAF (@ 8%, 4 years)] - $ 115000
= ($ 35497 x 3.3121) - $ 115000
= $ 2570.57
Project B = [$ 16817 x PVAF (@ 8%, 4 years)] - $ 49000
= ($ 16817 x 3.3121) - $ 49000
= $   6,700.04
Project B shall be adopted as per NPV
b) IRR
Year 0 Year 1 Year 2 Year 3 Year 4 IRR
Project A $ -1,15,000.00 $ 35,497.00 $ 35,497.00 $ 35,497.00 $ 35,497.00 9%
Project B $    -49,000.00 $ 16,817.00 $ 16,817.00 $ 16,817.00 $ 16,817.00 14%
Project B shall be selected as per IRR
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Dwight Donovan, the president of Zachary Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Zachary Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of five years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $109,000...
Dwight Donovan, the president of Baird Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Baird Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of four years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $111,000...
Dwight Donovan, the president of Stuart Enterprises is considering two investment opportunities. Because of limited resources...
Dwight Donovan, the president of Stuart Enterprises is considering two investment opportunities. Because of limited resources he will be able to only invest in one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of five years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $118,000...
Dwight Donovan, the president of Benson Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Benson Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of four years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $118,000...
Dwight Donovan, the president of Fanning Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Fanning Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of five years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $101,000...
Dwight Donovan, the president of Campbell Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Campbell Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of four years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $113,000...
Dwight Donovan, the president of Benson Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Benson Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of three years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $104,000...
Dwight Donovan, the president of Baird Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Baird Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of three years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $108,000...
Dwight Donovan, the president of Munoz Enterprises, is considering two investment opportunities. Because of limited resources,...
Dwight Donovan, the president of Munoz Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of three years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $103,000...
Pedro Spier, the president of Spier Enterprises, is considering two investment opportunities. Because of limited resources,...
Pedro Spier, the president of Spier Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of five years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $107,000...