Question

Tannenbaum Corporation uses the weighted average method in its process costing system. This month, the beginning...

Tannenbaum Corporation uses the weighted average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 400 units. The costs and percentage completion of these units in beginning inventory were:

                                                            Cost                % complete

            Materials costs                        5,700               65%

            Conversion costs                     6,800               45%

A total of 6,500 units were started and 5,900 units were transferred to the second processing department during the month. The first processing department incurred $125,500 of materials costs and $206,950 of conversion costs during the month.

The ending inventory was 50% complete with respect to materials and 35% complete with respect to conversion costs. Complete the following to determine the cost of ending WIP inventory in the first processing department (show calculations if needed):

Number of units in ending WIP

Materials

Conversion

Units transferred to the next department

+ Ending WIP

Equivalent units of production

Materials

Conversion

Cost of beginning WIP

+ Costs added during the period

Total cost

/ Equivalent units of production

Cost per equivalent unit

ENDING WORK-IN-PROCESS INVENTORY:

Materials

Conversion

TOTAL

Units in Ending WIP

x Cost per equivalent unit

Cost of Ending Work-in-Process inventory

           

Homework Answers

Answer #1

Calculate following :

Number of units in ending WIP
Material Conversion
Units transferred to the next department 5900 5900
+ Ending WIP (400+6500-5900) 1000*50% = 500 1000*35% = 350
Equivalent units of production 6400 6250
Material Conversion
Cost of beginning WIP 5700 6800
+ Costs added during the period 125500 206950
Total Cost 131200 213750
/ Equivalent units of production 6400 6250
Cost per equivalent unit 20.50 34.20
ENDING WORK-IN-PROCESS INVENTORY: Material Conversion Total
Units in Ending WIP 500 350
x Cost per equivalent unit 20.50 34.20
Cost of Ending Work-in-Process inventory 10250 11970 22220
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. Linton Inc. uses the weighted-average method in its process costing system. This month, the beginning...
1. Linton Inc. uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 800 units. The costs and percentage completion of these units in beginning inventory were Cost % complete Material costs 6,000 50% conversion costs 9900 30% A total of 9,200 units were started and 8,200 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department during...
Esty Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Esty Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 800 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 5,800 50% Conversion costs $ 6,500 30% A total of 7,700 units were started and 6,600 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Domingo Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Domingo Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 1,200 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 6,300 50% Conversion costs $ 2,500 20% A total of 7,600 units were started and 6,900 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Domingo Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Domingo Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 600 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 5,700 50% Conversion costs $ 1,900 20% A total of 7,000 units were started and 6,300 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Gunes Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Gunes Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 800 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 10,600 65% Conversion costs $ 12,800 30% A total of 8,500 units were started and 7,400 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 1,000 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 6,300 65% Conversion costs $ 7,400 45% A total of 7,700 units were started and 6,500 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Esty Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Esty Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 800 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 5,800 50% Conversion costs $ 6,500 30% A total of 7,700 units were started and 6,600 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 2,300 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 7,600 65% Conversion costs $ 8,700 45% A total of 10,300 units were started and 7,800 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Gunes Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Gunes Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 800 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 10,600 65% Conversion costs $ 12,800 30% A total of 8,500 units were started and 7,400 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Camino Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Camino Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 400 units. The costs and percentage completion of these units in beginning inventory were: Percent Complete Materials costs $      5,628 50% Conversion costs $      4,155 20% A total of 6,800 units were started and 6,100 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department during...