Cost of Goods Manufactured for a Manufacturing Company
The following information is available for Ethtridge Manufacturing Company for the month ending July 31
Cost of direct materials used in production | $148,600 |
Direct labor | 178,300 |
Work in process inventory, July 1 | 66,900 |
Work in process inventory, July 31 | 90,600 |
Total factory overhead | 81,700 |
Determine Ethtridge's cost of goods manufactured for the month ended July 31.
Ethtridge Manufacturing Company | ||
Statement of Cost of Goods Manufactured | ||
For the Month Ended July 31 | ||
$ | ||
Add manufacturing costs incurred during July: | ||
$ | ||
Total manufacturing costs incurred | ||
Total manufacturing costs | $ | |
Cost of goods manufactured | $ |
Ethtridge's cost of goods manufactured for the month ended July 31 | ||
Particulars | amount($) | |
Direct material | 148600 | |
Direct labour | 178300 | |
Overhead applied : | ||
Factory Overhead | 81700 | |
Total manfacturing cost | 408600 | |
Add : Beginning Work in process inventory | 66900 | |
475500 | ||
Less : Ending work in process inventory | -90600 | |
Cost of goods manfactured | 384900 | |
Cost of goods manfactured consists of all the goods completed during the period , it includes total manfacturing cost plus beginning work in process minus ending work in process, where as manfactuting costs include direct material used in production , direct labour and overheads. |