Question

Wayside Company has machine hours of 5,000 and machine costs ofS170,000 at the high data point....

Wayside Company has machine hours of 5,000 and machine costs ofS170,000 at the high data point. Machine hours are 2,000 and machine costs are S110,000 at the low data point. Wayside uses the high-low method to estimate costs.

1.Refer to Exhibit 5-4. What is the estimated cost per machine hour?
    $34
    $55
    $20
    $40
    None of the answer choices is correct.
2.Refer to Exhibit 5-4. What is the estimated total fixed cost?    $60,000
    $140,000
    $55,000
    $70,000
    None of the answer choices is correct.

  
  
3.Refer to Exhibit 5-4. What is the estimate of total machine costs at Wayside when 3,700 machine hours are used?
    $144,000
    $70,000
    $140,000
    $74,000
    None of the answer choices is correct.

Homework Answers

Answer #1

1.

Variable cost per hour= (Highest activity cost - Lowest activity cost)/(Highest activity - Lowest activity)

=( 170,000-110,000)/(5,000-2,000)

= 60,000/3,000

= $20 per machine hour

The estimated cost per machine hour is $20

Third option is correct.

2.

Fixed cost = Highest activity cost - Highest activity x Variable cost per hour

= 170,000- 5,000 x 20

= 170,000-100,000

= $70,000

The estimated total fixed cost $70,000

Fourth option is correct

3.

The estimated total machine costs at Wayside when 3,700 machine hours are used

= Fixed cost + Variable cost per hour x Activity hour

= 70,000 + 20 x 3,700

= 70,000+74,000

= $144,000

1st option is correct.

Please give a positive rating if you are satisfied with this solution and if you have any query kindly ask.Thanks!!!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
At the high level of activity in November, 9000 machine hours were run and power costs...
At the high level of activity in November, 9000 machine hours were run and power costs were $16000. In April, a month of low activity, 3000 machine hours were run and power costs amounted to $7000. Using the high-low method, the estimated fixed cost element of power costs is
Machine Master, Inc. had the following data regarding monthly power costs: Month Machine hours Power cost...
Machine Master, Inc. had the following data regarding monthly power costs: Month Machine hours Power cost Jan 300 $650 Feb 600 720 Mar 400 685 Apr 200 640 May 350 675 Use the high-low method, estimate the cost formula regarding monthly power costs Assume that management expects 500 machine hours in May. Calculate May’s power cost using machine hours as the basis for prediction.
Great Eagle Company allocates overhead based on machine hours. They estimated overhead costs for the year...
Great Eagle Company allocates overhead based on machine hours. They estimated overhead costs for the year to be $380,000. Estimated machine hours was 5,000 and direct labor hours was 2,000. Estimated direct labour cost was $250,000 and direct material cost was $140,000. Actual hours and overhead costs for the year were 4,300 machine hours and $310,000 of overhead. Required:        Calculate the overhead application rate for the year. What is the amount of applied overhead for the year? What is the...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 3,500 $ 18,900 February 3,900 $ 22,000 March 2,900 $ 14,000 April 4,100 $ 24,000 May 4,800 $ 28,750 June 4,300 $ 23,000 July 5,500 $ 25,250 August 4,500 $ 23,250 September 3,000 $ 16,500 October 4,700 $ 27,000 November...
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows:...
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows: Month Electricity Costs Machine Hours January $12,600 8000 February 14,333 9600 March 9,333 5600 April 15,667 10200 May 19,167 9200 June 15,134 13200 July 16,834 14400 August 15,500 12000 September 10,667 6000 October 17,667 13200 November 21,000 16800 Required: a. Using the high-low method, develop an estimate of variable electricity costs per machine hour. b. Using the high-low method, develop an estimate of fixed...
The Manoli Company has collected the following data for use in calculating product costs: Activity Data:...
The Manoli Company has collected the following data for use in calculating product costs: Activity Data: (expected and actual) rug cleaners         sweepers      total units produced                   100,000                  250,000           350,000 prime costs                        $200,000                $584,000           $784,000 direct labor hours    10,000                              40,000                    50,000 machine hours                   20,000                              10,000                      30,000 number of setups    25                                     75                           100 inspection hours                1,600           ...
Slonaker Inc. has provided the following data concerning its maintenance costs: Machine-Hours Maintenance Cost   April 5,799...
Slonaker Inc. has provided the following data concerning its maintenance costs: Machine-Hours Maintenance Cost   April 5,799           $30,379           May 5,782           $30,289           June 5,764           $30,237           July 5,761           $30,233           August 5,717           $30,078           September 5,795           $30,360           October 5,809           $30,388           November 5,801           $30,378           December 5,785           $30,318         Management believes that maintenance cost is a mixed cost that depends on machine-hours. Required: Estimate the variable cost per machine-hour and...
Q.1 For Divaxo Company, labor-hours are 28,000 and wages $126,000 at the high point of the...
Q.1 For Divaxo Company, labor-hours are 28,000 and wages $126,000 at the high point of the relevant range, and labor-hours are 20,000 and wages $102,000 at the low point of the relevant range. What is the estimated total labor costs at Divaxo Company when 11,100 labor-hours are used? $52,725 $75,300 $49,950 $56,610
Moresan Co. gathered the following information on power costs and factory machine usage for the last...
Moresan Co. gathered the following information on power costs and factory machine usage for the last six months: Month Power Costs $ Factory Machine Hours January 18,000 10,000 February 16,650 9,000 March 18,600 10,600 April 16,200 8,800 May    17,100 9,500 June        16,900 9,350 Using the high-low method of analyzing costs, ans Using the high-low method of analyzing costs, answer the following questions, and show computations to support your answers. (1) Compute      a) the variable cost (5 points)      b)...
Uninder Company uses the high-low method to estimate the cost function. The information for 2015 is...
Uninder Company uses the high-low method to estimate the cost function. The information for 2015 is provided below:                                                                 Machine-hours       Labor Costs       Highest observation of cost driver                 550                   $22,000       Lowest observation of cost driver                  250                  $ 13,000 What is the estimated total cost when 400 machine-hours are used?    a. $17,500     b. $29,000     c. $16,000     d. $20,800