Question

Required information [The following information applies to the questions displayed below.] A manufactured product has the...

Required information

[The following information applies to the questions displayed below.]

A manufactured product has the following information for June.

Standard Actual
Direct materials 7 lbs. @ $8 per lb. 62,900 lbs. @ $8.10 per lb.
Direct labor 3 hrs. @ $17 per hr. 26,400 hrs. @ $17.50 per hr.
Overhead 3 hrs. @ $13 per hr. $ 352,500
Units manufactured 8,900

(1) Compute the standard cost per unit.
(2) Compute the total cost variance for June.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Required information [The following information applies to the questions displayed below.] A manufactured product has the...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 7 lbs. @ $8 per lb. 62,900 lbs. @ $8.10 per lb. Direct labor 3 hrs. @ $17 per hr. 26,400 hrs. @ $17.50 per hr. Overhead 3 hrs. @ $13 per hr. $ 352,500 Units manufactured 8,900 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance...
[The following information applies to the questions displayed below.] A manufactured product has the following information...
[The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 6 lbs. @ $8 per lb. 44,800 lbs. @ $8.20 per lb. Direct labor 3 hrs. @ $17 per hr. 21,900 hrs. @ $17.60 per hr. Overhead 3 hrs. @ $12 per hr. $ 272,900 Units manufactured 7,400 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question by entering...
[The following information applies to the questions displayed below.] A manufactured product has the following information...
[The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 5 lbs. @ $8 per lb. 40,000 lbs. @ $8.20 per lb. Direct labor 2 hrs. @ $16 per hr. 15,400 hrs. @ $16.50 per hr. Overhead 2 hrs. @ $12 per hr. $ 195,800 Units manufactured 7,900 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question by entering...
Use the following information for the Exercises below. [The following information applies to the questions displayed...
Use the following information for the Exercises below. [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials (7 lbs. @ $7 per lb.) 62,900 lbs. @ $7.10 per lb. Direct labor (3 hrs. @ $16 per hr.) 26,500 hrs. @ $16.50 per hr. Overhead (3 hrs. @ $13 per hr.) $ 352,600 Units manufactured 8,900 Exercise 23-8 Standard unit cost; total cost variance LO C2 (1) Compute...
A manufactured product has the following information for June.
A manufactured product has the following information for June.StandardActualDirect materials5 lbs. @ $8 per lb.38,000lbs. @ $8.10 per lb.Direct labor3 hrs. @ $16 per hr.22,200hrs. @ $16.40 per hr.Overhead3 hrs. @ $11 per hr.$252,700Units manufactured7,500(1) Compute the standard cost per unit.(2) Compute the total cost variance for June.Direct materials :Direct labor:Overhead:Total :Total cost variance:
A manufactured product has the following information for June.
A manufactured product has the following information for June.StandardActualDirect materials5 lbs. @ $8 per lb.38,000lbs. @ $8.10 per lb.Direct labor3 hrs. @ $16 per hr.22,200hrs. @ $16.40 per hr.Overhead3 hrs. @ $11 per hr.$252,700Units manufactured7,500(1) Compute the standard cost per unit.(2) Compute the total cost variance for June.Direct materials :Direct labor:Overhead:Total :Total cost variance:
Use the following information for the Exercises below. [The following information applies to the questions displayed...
Use the following information for the Exercises below. [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 7 lbs. @ $7 per lb. 56,400 lbs. @ $7.10 per lb. Direct labor 3 hrs. @ $16 per hr. 23,600 hrs. @ $16.50 per hr. Overhead 3 hrs. @ $12 per hr. $ 293,100 Units manufactured 8,000 Exercise 08-9 Direct materials variances LO P3 Compute the direct materials price...
Check my workCheck My Work button is now enabled Item 7 Item 7 Part 1 of...
Check my workCheck My Work button is now enabled Item 7 Item 7 Part 1 of 3 10 points Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 7 lbs. @ $8 per lb. 60,100 lbs. @ $8.20 per lb. Direct labor 2 hrs. @ $15 per hr. 16,800 hrs. @ $15.50 per hr. Overhead 2 hrs. @ $12 per hr. $ 209,800 Units manufactured...
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per...
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per unit @ $12.50 per lb. Direct labor 0.5 hours per unit @ $96 per hour Overhead $132 per direct labor hour Units manufactured 16,000 Total manufacturing costs $ 2,216,400 (1) Compute the standard cost per unit. (2) Compute the total budgeted cost for production in August. (3) Compute the total cost variance for August. (Indicate the effect of each variance by selecting for favorable,...
8. [The following information applies to the questions displayed below.] Sedona Company set the following standard...
8. [The following information applies to the questions displayed below.] Sedona Company set the following standard costs for one unit of its product for this year. Direct material (20 Ibs. @ $3.20 per Ib.) $ 64.00 Direct labor (10 hrs. @ $8.30 per hr.) 83.00 Variable overhead (10 hrs. @ $4.70 per hr.) 47.00 Fixed overhead (10 hrs. @ $2.30 per hr.) 23.00 Total standard cost $ 217.00 The $7.00 ($4.70 + $2.30) total overhead rate per direct labor hour...