Question

Swan Company has a direct labor standard of 15 hours per unit of output. Each employee...

Swan Company has a direct labor standard of 15 hours per unit of output. Each employee has a standard wage rate of $14 per hour. During March, employees worked 13,100 hours. The direct labor rate variance was $9,170 favorable, and the direct labor efficiency variance was $15,400 unfavorable. How many units were produced?

  • 655 units

  • 1,100 units

  • 800 units

  • 873 units

Homework Answers

Answer #1

If You Have Any Queries Please Do Comment

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Swan Company has a direct labor standard of 35 hours per unit of output. Each employee...
Swan Company has a direct labor standard of 35 hours per unit of output. Each employee has a standard wage rate of $34 per hour. During March, employees worked 15,100 hours. The direct labor rate variance was $11,170 favorable, and the direct labor efficiency variance was $17,400 unfavorable. What was the actual labor costs? $502,230 $524,570 $513,400 $496,000
Madrid Co. has a direct labor standard of 4 hours per unit of output. Each employee...
Madrid Co. has a direct labor standard of 4 hours per unit of output. Each employee has a standard wage rate of $13.00 per hour. During February, Madrid Co. paid $99,600 to employees for 9,240 hours worked. 2,480 units were produced during February. What is the direct labor efficiency variance? $20,520 favorable $29,360 favorable $8,840 favorable $19,672 favorable
The Vienna Company, which manufactures violins, has established the following standard cost per violin: Standard Qty/Hours...
The Vienna Company, which manufactures violins, has established the following standard cost per violin: Standard Qty/Hours Standard Price/Rate Standard Cost Direct material 3 pounds $4.00 per pound $12.00/violin Direct labor 2 hours $8.00 per hour $16.00/violin Variable mfg overhead 2 hours $5.00 per hour $10.00/violin Vienna produced 600 violins. To produce the violins, employees worked 1,100 direct labor hours and total variable manufacturing overhead spending was $5,720. Variable manufacturing overhead is based upon direct labor hours. Vienna's variable overhead rate...
The standard direct labor cost per unit for a company was $24 (= $15 per hour...
The standard direct labor cost per unit for a company was $24 (= $15 per hour × 1.6 hours per unit). During the period, actual direct labor costs amounted to $145,600, 9,500 labor-hours were worked, and 6,600 units were produced. Required: Compute the direct labor price and efficiency variances for the period. (Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.)
At Roger, the standard quantity of labor is 25 hours per refrigeration unit. The standard wage...
At Roger, the standard quantity of labor is 25 hours per refrigeration unit. The standard wage rate is $36. In July, the company produced 83 refrigeration units and incurred 2,100 labor hours at a cost of $65,100. Calculate the labor rate variance and the labor efficiency variance. Indicate whether the variances are favorable or unfavorable. (Round intermediate calculations to 2 decimal places, e.g. 14.37 and final answers to 0 decimal places, e.g. 125. Enter all variances as a positive number.)...
Bellingham Company produces a product that requires 10 standard direct labor hours per unit at a...
Bellingham Company produces a product that requires 10 standard direct labor hours per unit at a standard hourly rate of $22.00 per hour. If 4,300 units used 41,300 hours at an hourly rate of $23.10 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance $ Unfavorable b....
The standard direct labor cost for producing one unit of product is 5 direct labor hours...
The standard direct labor cost for producing one unit of product is 5 direct labor hours at a standard rate of pay of $12. Last month, 15,000 units were produced and 73,500 direct labor hours were actually worked at a total cost of $810,000. The direct labor quantity variance was A) $18,000 favorable B) $18,000 unfavorable c) $27,000 unfavorable D) $27,000 favorable
Direct Labor Variances Bellingham Company produces a product that requires 5 standard direct labor hours per...
Direct Labor Variances Bellingham Company produces a product that requires 5 standard direct labor hours per unit at a standard hourly rate of $17.00 per hour. If 5,300 units used 25,700 hours at an hourly rate of $17.68 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...
Winle Corp has a standard cost system and applies overhead based on direct labor hours. The...
Winle Corp has a standard cost system and applies overhead based on direct labor hours. The standards for manufacturing overhead are as follow: Standard labor hours per unit of product 1.4 Standard manufacturing overhead cost 22.00 per hour During the current period, Winle worked 1,500 hours to produce 1,000 units. Total actual manufacturing overhead cost was $30,000. What was the manufacturing overhead rate variance for the month? Multiple Choice $800 Unfavorable $3,000 Favorable $3,000 Unfavorable $800 Favorable
Glavine & Co. produces a single product, each unit of which requires three direct labor hours...
Glavine & Co. produces a single product, each unit of which requires three direct labor hours (DLHs). Practical capacity (for setting the factory overhead application rate) is 42,000 DLHs, on an annual basis. The information below pertains to the most recent year: Standard direct labor hours (DLHs) per unit produced 3.00 Practical capacity, in DLHs (per year) 42,000 Variable overhead efficiency variance $ 11,000 unfavorable (U) Actual production for the year 12,500 units Budgeted fixed manufacturing overhead $ 840,000 Standard...