Question

Bob the Builder purchased land as a factory site for $282,000. He paid $10,000 to tear...

Bob the Builder purchased land as a factory site for $282,000. He paid $10,000 to tear down two buildings on the land, and the salvage from these old buildings was sold for $1,350. Legal fees of $870 were paid for title investigation and making the purchase. Architect's fees were $10,300. Liability insurance during construction cost $650. Excavation costs were $2,610. A contractor was paid $600,000 to construct the new building. An assessment made by the city for pavement was $1,600. Interest costs during construction were $42,500. Assume that Bob prepares his financial statements based on IFRS. Determine the cost of land to be capitalized.

Homework Answers

Answer #1
Cost of Land
Amount in $
Factory Site        282,000
Add:Paid to Tear down           10,000
Less: Salvage            -1,350
Add: Legal fee                 870
Add: Assessment by city for pavement             1,600
Cost of land to be capitalized.       293,120
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down...
Wilson Co. purchased land as a factory site for $600,000. Wilson paid $60,000 to tear down two buildings on the land. Salvage was sold for $5,400. Legal fees of $3,480 were paid for title investigation and making the purchase. Architect's fees were $31,200. Title insurance cost $2,400, and liability insurance during construction cost $2,600. Excavation cost $10,440. The contractor was paid $2,200,000. An assessment made by the city for pavement was $6,400. Interest costs during construction were $170,000. (compute cost...
Waterway Industries purchased land as a factory site for $1315000. Waterway paid $117000 to tear down...
Waterway Industries purchased land as a factory site for $1315000. Waterway paid $117000 to tear down two buildings on the land. Salvage was sold for $8400. Legal fees of $5480 were paid for title investigation and making the purchase. Architect's fees were $47000. Title insurance cost $3700, and liability insurance during construction cost $4000. Excavation cost $15800. The contractor was paid $4200000. An assessment made by the city for pavement was $9800. Interest costs during construction were $252000. The cost...
Vaughn Manufacturing purchased land as a factory site for $1330000. Vaughn paid $112000 to tear down...
Vaughn Manufacturing purchased land as a factory site for $1330000. Vaughn paid $112000 to tear down two buildings on the land. Salvage was sold for $8100. Legal fees of $5000 were paid for title investigation and making the purchase. Architect's fees were $46300. Title insurance cost $3500, and liability insurance during construction cost $3800. Excavation cost $15440. The contractor was paid $4400000. An assessment made by the city for pavement was $9600. Interest costs during construction were $257000. The cost...
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down...
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $ 62,160 to raze the old buildings and sold salvaged lumber and brick for $ 9,324. Legal fees of $ 2,738 were paid for title investigation and drawing the purchase contract. Sage paid $ 3,256 to an engineering firm for a land survey, and $ 100,640 for drawing...
Martin Buber Co. purchased land as a factory site for $758,400. The process of tearing down...
Martin Buber Co. purchased land as a factory site for $758,400. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $79,632 to raze the old buildings and sold salvaged lumber and brick for $11,945. Legal fees of $3,508 were paid for title investigation and drawing the purchase contract. Martin Buber paid $4,171 to an engineering firm for a land survey, and $128,928 for drawing the factory plans. The...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21000 Architect's fees 36000 Legal fees for title investigation and purchase contract 5300 Construction costs 1392000 (Salvaged materials resulting from demolition were sold for $10800.) Crane should record...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for $325000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21300 Architect's fees 33900 Legal fees for title investigation and purchase contract 5400 Construction costs 1379000 (Salvaged materials resulting from demolition were sold for $9600.) Coronado should record...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2017. Costs incurred during this period are listed below: Demolition of old building $3300 Architect's fees for new building $13578 Legal fees for title investigation of land $1649 Property taxes on land for period beginning March 1, 2016 $2084 Construction costs $552822 Interest on construction...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2018) 4,100 Construction costs 610,000 Interest on...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT