Question

A building was constructed last year for Agro Co. for use as a production facility. Construction...

  1. A building was constructed last year for Agro Co. for use as a production facility. Construction began on January 1 and was completed on December 31. The payments to the contractor were as follows.

Date

Payment

1/1

$300,000

4/1

  620,000

8/1

  460,000

10/1

  300,000

To finance construction of the building, a $750,000, 10% construction loan was taken out on January 1. The loan was repaid on December 31. The firm had two sources of general debt: $400,000 note payable, 9% annual interest, and $500,000 par value bonds, 7.5% annual interest.

Determine the amount of interest to be capitalized.

Homework Answers

Answer #1

Solution:

Weighted-Average accumulated expenditure
Date Amount Capitalization period Weighted Average Accumulated Expenditures
1-Jan $300,000 12/12 $300,000
1-Apr $620,000 9/12 $465,000
1-Aug $460,000 5/12 $191,667
1-Oct $300,000 3/12 $75,000
Total $1,680,000 $1,031,667
Weighted average interest rate of all other debt
Debt Amount Interest rate Interest amount
9% Note $400,000 9.00% $36,000
7.50% Note $500,000 7.50% $37,500
Totals $900,000 $73,500
Weighted average rate (total interets/ total debt) 8.17%

amount of interest to be capitalized = ($750,000*10%) + ($1,031,667 - $750,000)* 8.17%

= $75,000 + $23,012

= $98,012

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $11,500,000 and an effective interest rate of 10%. Construction expenditures incurred during 2018 were as follows: January 1 $ 650,000 March 1 690,000 July 31 570,000 September 30 750,000 December 31 450,000 Date Expenditure Weight Average January 1...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,050,000 at 11% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $6,000,000, 16% bonds $4,000,000, 11% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 840,000 March 31 1,440,000 June 30 1,088,000 September 30 840,000...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,350,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 14% bonds $3,000,000, 9% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 960,000 March 31 1,560,000 June 30 1,232,000 September 30 960,000...
Azalea Company began construction on a new office building on Jan. 1 of this year. The...
Azalea Company began construction on a new office building on Jan. 1 of this year. The building was completed on Sept. 30. Expenditures were made of $200,000 on Jan. 1; $300,000 on Sept. 1; and $300,000 on Dec. 31. The weighted average accumulated expenditures are: Group of answer choices $500,000 $300,000 $350,000 $400,000
Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its...
Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $258,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 275,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was outstanding for the...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be used as its office headquarters. The building was completed on June 30, 2019. Expenditures on the project, mainly payments to subcontractors, were as follows: January 1, 2018 $500,000 March 31, 2018 $400,000 September 30, 2018 $600,000 Accumulated expenditures at December 31, 2018 $1,500,000 (before interest capitalization) January 31, 2019 $600,000 April 30, 2019 $300,000 On January 1, 2018, the company obtained a $1,000,000 construction...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new...
Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was...