Question

Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:

Machine-hours required to support estimated production 156,000
Fixed manufacturing overhead cost $ 653,000
Variable manufacturing overhead cost per machine-hour $ 4.30

Required:

1. Compute the plantwide predetermined overhead rate.

2. During the year, Job 400 was started and completed. The following information was available with respect to this job:

Direct materials $ 340
Direct labor cost $ 290
Machine-hours used 40

Compute the total manufacturing cost assigned to Job 400.

3. If Job 400 includes 60 units, what is the unit product cost for this job?

4. If Moody uses a markup percentage of 130% of its total manufacturing cost, then what selling price per unit would it have established for Job 400?

Questions:

1. Predetermined overhead rate ______ per MH (Round answer to 2 decimal spaces)

2. Total manufacturing cost ______ (Round your intermediate calculations to 2 decimal places and your final answer to the nearest dollar amount.)

3. If Job 400 includes 60 units, what is the unit product cost for this job? (Round your intermediate calculations and final answer to the nearest whole dollar.)

unit product cost _____

4. If Moody uses a markup percentage of 130% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? (Round your intermediate calculations and final answer to the nearest whole dollar.)

Selling price per unit _____

Homework Answers

Answer #1
  • Requirement 1

A

Fixed manufacturing Overhead

$653,000

B

Machine hours

                      156,000

C = A/B

Fixed overhead per machine hour

$4.19

D

Variable overhead per machine hour

$4.30

E = C+D

Plantwide Overhead rate

$8.49

Answer

  • Working

A

Machine hours used

40

B

Plantwide Overhead rate

$8.49

C = A x B

Manufacturing Cost assigned to Job 400

$340

  • Requirement 2

A

Direct material

$340

B

Direct Labor

$290

C

Manufacturing Cost assigned to Job 400

$340

D = A+B+C

Total Cost

$970 Answer

  • Requirement 3

Unit product Cost = $ 970 / 60 units = $ 16.17 or $ 16 per unit

  • Requirement 4

Selling price per unit = $ 16 + (16 x 130%) = 16 + 21 = $ 37 per unit

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 159,000 Fixed manufacturing overhead cost $ 651,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 654,000 Variable manufacturing overhead cost per machine-hour $ 4.70 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 152,000 Fixed manufacturing overhead cost $ 654,000 Variable manufacturing overhead cost per machine-hour $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 155,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:      Machine-hours required to support estimated production 158,000 Total estimated manufacturing overhead cost $ 1,406,200 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined Overhead Rate: _________     2. During the year, Job 400 was started and completed. The following information was...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production 200,000 Fixed manufacturing overhead cost $1,300,000 Variable manufacturing overhead cost per machine-hour $3.00 1.a - Compute the predetermined overhead rate – (12 points) 1. b - During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:     Machine-hours required to support estimated production . . . . . . 100,000     Fixed manufacturing overhead cost . . . . . . . . . . . . . . . . . . . . . . . . $650,000    Variable manufacturing overhead cost per machine-hour . ....
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 42,000 direct labor-hours, total fixed manufacturing overhead cost of $361,200, and a variable manufacturing overhead rate of $2.40 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours 200...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 38,000 direct labor-hours, total fixed manufacturing overhead cost of $250,800, and a variable manufacturing overhead rate of $2.40 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours 400...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT