Great Products Company currently outsources a relay switch that
is a component in one of its products. The switches cost $40 each.
The company is considering making the switches internally at the
following projected annual production costs:
Unit-level material cost | $8 |
Unit-level labor cost | $7 |
Unit-level overhead | $6 |
Batch-level set-up cost (4,000 units per batch) | $30,000 |
Product-level supervisory salaries | $40,000 |
Allocated facility-level costs | $25,000 |
The company expects an annual need for 4,000 switches. If the
company makes the product, it will have to utilize factory space
currently being leased to another company for $2,000 a month. If
the company decides to make the parts, total costs will be which
choice below:?
$25,000 less than if the switches are purchased.
$43,000 more than if the switches are purchased.
$22,000 less than if the switches are purchased.
$18,000 more than if the switches are purchased.
Cost of making parts
Unit-level material cost (4,000 x 8) | 32,000 |
Unit-level labor cost (4,000 x 7) | 28,000 |
Unit-level overhead (4,000 x 6) | 24,000 |
Batch-level set-up cost | 30,000 |
Product-level supervisory salaries | 40,000 |
Allocated facility-level costs | 25,000 |
Opportunity cost (2,000 x 12) | 24,000 |
Total cost of making | $203,000 |
Cost of buying = Outside supplier's price + Allocated facility level cost
= (4,000 x 40) + 25,000
= $185,000
Thus, if the company decides to make the parts, total cost will be $18,000 (203,000 - 185,000) more than if the switches are purchased.
Fourth option is the correct option.
Get Answers For Free
Most questions answered within 1 hours.