Question

Marie Designers is a maker of designer dresses. The cost of each dress is the sum...

Marie Designers is a maker of designer dresses. The cost of each dress is the sum of three variable costs (direct material costs, direct labour costs, and overhead costs) and one fixed-cost category (overhead costs). Variable overhead cost is allocated to each dress on the basis of budgeted direct labour-hours per dress. For June 2020, each dress is budgeted to take 8 labour hours. Budgeted variable overhead cost per labour-hour is $18. The budgeted number of dresses to be made in June 2020 is 2,080.

Actual variable costs in June 2020 were $104,328 for 2,160 dresses started and completed. There were no beginning or ending inventories of dresses. Actual direct labour-hours for June were 9,072.

  1. Compute the flexible-budget variance, the spending variance, and the efficiency variance for variable manufacturing overhead.

                        

Question 4 continued over next page

Question 4 continued

  1. Comment on the spending and efficiency variances calculated.

___________________________________________________________________

___________________________________________________________________

___________________________________________________________________

___________________________________________________________________

___________________________________________________________________

Homework Answers

Answer #1
Computation of Variances
Budgeted Labour Hours for each Dress 8
Budgeted Variable overhead cost per Labour hours 18
Budgeted quantity 2,080
Actual Variable cost 1,04,328
Actual quantity 2,160
Actual Labour Hours 9,072
Standard Hours 17,280
Standard Cost 3,11,040
Flexible Budget Variance = Standard Cost- Actual Cost
=3,11,040 - 1,04,328
2,06,712 Favorable
Spending Variance = (Budgted rate - Actual rate)* Actual Hours
= BR X AH - AR X AH
=18 X 9,072 - 1,04,328
58,968 Favorable
Efficiency Variance for Manufacturing overhead = (Standard hours - Actual hours)X Budgeted Rate
=(17,280 -9072) X 18
1,47,744 Favorable
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Question 3: Stafford Clothing is a manufacturer of designer suits. The cost of each suit is...
Question 3: Stafford Clothing is a manufacturer of designer suits. The cost of each suit is the sum of three variable costs (direct material costs, direct manufacturing labour costs, and manufacturing overhead costs), and one fixed-cost category (manufacturing overhead costs).Variable manufacturing overhead cost is allocated to each suit based on budgeted direct manufacturing labour-hours per suit. For June 2019, each suit is budgeted to take 4.5 labour-hours. Budgeted variable manufacturing overhead cost per labour-hour is $11. The budgeted number of...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes...
The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes direct materials, direct labor, and manufacturing (factory) overhead. The firm traces all direct costs to products, and it assigns overhead cost to products based on direct labor hours. The company budgeted $10,045 variable factory overhead cost and 2,050 direct labor hours to manufacture 4,100 pairs of boots in March. The factory used 3,800 direct labor hours in March to manufacture 3,900 pairs of boots...
The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes...
The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes direct materials, direct labor, and manufacturing (factory) overhead. The firm traces all direct costs to products, and it assigns overhead cost to products based on direct labor hours. The company budgeted $15,000 variable factory overhead cost and 2,500 direct labor hours to manufacture 5,000 pairs of boots in March. The factory used 2,700 direct labor hours in March to manufacture 4,800 pairs of boots...
1) MNO produces a single product. The standard production requirement for each unit requires 0.50 direct...
1) MNO produces a single product. The standard production requirement for each unit requires 0.50 direct labour hours at a standard rate of $11 per hour. During the last year, MNO assembly line workers worked a total of 5,000 hours at a cost of $50,000 to MNO. Also last year, MNO manufactured 3,000 units of product. What was the company's direct labour rate variance for the year? 2) MNO produces a single product. The standard production requirement for each unit...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Planned production—units 50 000 Direct labour hours 200 000 Variable overhead $ 1 000 000 Fixed overhead $ 600 000 The following were the actual results Actual production—units 48 000 Direct labour hours 195 000 Variable overhead $ 950 000 Fixed overhead $ 610 000 Calculate the...
The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes...
The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes direct materials, direct labor, and manufacturing (factory) overhead. The firm traces all direct costs to products, and it assigns overhead cost to products based on direct labor hours. The company budgeted $13,110 variable factory overhead cost and 2,300 direct labor hours to manufacture 4,600 pairs of boots in March. The factory used 3,200 direct labor hours in March to manufacture 4,300 pairs of boots...
Budgeted Variable overhead for the year is $120000. Expected activity is 20000 standard direct labour hours....
Budgeted Variable overhead for the year is $120000. Expected activity is 20000 standard direct labour hours. Actual hours work were 18000 and standard hours allowed for actual production were 19500. What is the variable overhead efficiency variance?
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)   ...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,100 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT