Question

  Standard variable overhead rate per hour $1   Standard fixed overhead rate per hour $2   Planned monthly...

  Standard variable overhead rate per hour

$1

  Standard fixed overhead rate per hour

$2

  Planned monthly activity

40,000 machine hours

  Actual production completed

82,000 units

  Standard machine processing time

Two units per hour

  Actual variable overhead

$37,000

  Actual total overhead

$121,000

  Actual machine hours worked

40,500

                  All of the company's overhead is variable or fixed in nature.

                  

                  Required:

                  1.     Calculate the spending and efficiency variances for variable overhead.

                  2.     Calculate the SPENDING and PRODUCTION volume variances for fixed overhead.

Homework Answers

Answer #1

Solution 1:

Standard machine hours for actual production = 82000/2 = 41000 hours

Actual machine hours worked = 40500 hours

Standard rate of variable overhead = $37,000 / 40500 = $0.91358 per machine hour

Actual rate of variable overhead = $1 per machine hour

Variable overhead spending variance = (SR - AR) * AH = ($1 - 0.91358) * 40500 = $3,500 F

Variable overhead efficiency variance = (SH - AH) * SR = (41000 - 40500) * $1 = $500 F

Solution 2:

Budgeted fixed overhead = 40000*$2 = $80,000

Actual fixed overhead = $121,000 - $37,000 = $84,000

Fixed overhead applied = SH * SR = 41000 * $2 = $82,000

Fixed overhead spending variance = Budgeted fixed overhead - Actual fixed overhead

= $80,000 - $84,000 = $4,000 U

Fixed overhead volume variance = Fixed overhead applied - Budgeted fixed overhead = $82,000 - $80,000 = $2,000 F

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Draco, Inc. has the following overhead standards: Variable overhead: 4 hours at $8 per hour Fixed...
Draco, Inc. has the following overhead standards: Variable overhead: 4 hours at $8 per hour Fixed overhead: 4 hours at $10 per hour The standards were based on a planned activity of 20,000 machine hours when 5,000 units were scheduled for production. Actual data follow. Variable overhead incurred: $167,750 Fixed overhead incurred: $210,000 Machine hours worked: 19,800 Actual units produced: 5,100 Duncanville’s fixed-overhead volume variance is: Duncanville’s variable-overhead efficiency variance is: The amount of variable overhead that Duncanville applied to...
FIXED OVERHEAD SPENDING AND VOLUME ARIANCES, COLUMNAR AND FORMULA APPROACHES A company provided the following information:...
FIXED OVERHEAD SPENDING AND VOLUME ARIANCES, COLUMNAR AND FORMULA APPROACHES A company provided the following information: Standard fixed overhead rate (SFOR) per direct labour hour    $7.00 Actual fixed overhead rate (AFOR) per direct labour hour        $6.95 Actual direct labour hours worked (AH)                                      36,100 Actual production in units                                                              12,000 Standard hours allowed for actual units produced (SH)          36,000 Required: Using the columnar approach, calculate the fixed overhead spending and efficiency variances. Using the formula approach, calculate the fixed overhead spending variance. Using the formula approach, calculate...
Variable Overhead Spending and Efficiency Variances, Columnar and Formula Approaches Rath Company provided the following information:...
Variable Overhead Spending and Efficiency Variances, Columnar and Formula Approaches Rath Company provided the following information: Standard variable overhead rate (SVOR) per direct labor hour $3.75 Actual variable overhead costs $222,816 Actual direct labor hours worked (AH) 57,200 Actual production in units 15,000 Standard hours (SH) allowed for actual units produced 60,000 Required: 1. Using the columnar approach, calculate the variable overhead spending and efficiency variances. Enter amounts as positive numbers. (1) (2) (3)                   Spending Efficiency...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)   ...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.50 Standard fixed-overhead rate per hour: $12.40 Planned activity during the period: 19,000 machine hours Actual production: 12,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $153,180 Actual total overhead: $432,900 Actual machine hours worked: 22,200 Required: 1. Calculate the...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $2.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $384,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $4.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.20 per hour. The company planned to operate at a...
Problem: The following selected information was extracted from the accounting records of Austin, Inc.: Planned manufacturing...
Problem: The following selected information was extracted from the accounting records of Austin, Inc.: Planned manufacturing activity: 40,000 machine hours Standard variable-overhead rate per machine hour: $16 Budgeted fixed overhead: $100,000 Variable-overhead spending variance: $92,000 U Variable-overhead efficiency variance: $102,000 F Fixed-overhead budget variance: $25,000 U Total actual overhead: $675,000 Actual fixed overhead: $125,000 Fixed Actual variable overhead: $550,000 Variable Actual machine hours worked: 28,625 Standard machine hours allowed: 35,000 Need to find Fixed-overhead volume variance I already know the...
Riviera Beach Pink Flamingos has the following standards and flexible-budget data. Standard variable-overhead rate $6.00 per...
Riviera Beach Pink Flamingos has the following standards and flexible-budget data. Standard variable-overhead rate $6.00 per direct-labor hour Standard quantity of direct labor 2 hours per unit of output Budgeted fixed overhead $100,000 Budgeted output 25,000 units Actual results for April are as follows: Actual output 20,000 units Actual variable overhead $320,000 Actual fixed overhead $97,000 Actual direct labor 50,000 hours Required: 1.Use the variance formulas to compute the following variances .Indicate whether each variance is favorable or unfavorable,where appropriate...
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine       &n
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine         Machine-Hours   Overhead Costs            hour)  8,000    9,000    10,000 Variable costs   $1.05  $ 8,400 $ 9,450 $10,500 Fixed costs       24,800   24,800   24,800 Total Overhead Costs    $33,200 $34,250 $35,300 The following information is available for a recent period: a. The denominator activity of 8,000 machine-hours was chosen to compute the predetermined overhead rate. b. At the 8,000 standard machine-hours level of activity, the company should produce 3,200 units of product. c....
The following information is for the third quarter of this year: Planned Actual Production 92,000 units...
The following information is for the third quarter of this year: Planned Actual Production 92,000 units 87,000 units Direct labor hours 506,000 DL hrs 380,000 DL hrs    Fixed manufacturing overhead $205,000 $182,400 Variable manufacturing overhead $910,000 $841,500 Standard direct labor hour per unit 5.5 Required: Calculate the following three overhead variances, overhead is allocated based on direct labor hours: 1. Overhead volume variance 2. Overhead efficiency variance 3. Overhead spending variance 4. Formulate a hypothesis about the cause of...