Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 11,000 hours of productive capacity in the department:

Variable overhead costs:
   Indirect factory labor $106,700
   Power and light 4,400
   Indirect materials 29,700
      Total variable overhead cost $140,800
Fixed overhead costs:
   Supervisory salaries $49,280
   Depreciation of plant and equipment 30,980
   Insurance and property taxes 19,710
      Total fixed overhead cost 99,970
Total factory overhead cost $240,770

Assuming that the estimated costs for November are the same as for October, prepare a flexible factory overhead cost budget for the Press Department for November for 9,000, 11,000, and 13,000 hours of production. Round your interim computations to the nearest cent, if required. Enter all amounts as positive numbers.

Leno Manufacturing Company
Factory Overhead Cost Budget-Press Department
For the Month Ended November 30
Direct labor hours 9,000 11,000 13,000
Variable overhead costs:
Indirect factory labor $ $ $
Power and light
Indirect materials
Total variable factory overhead $ $ $
Fixed factory overhead costs:
Supervisory salaries $ $ $
Depreciation of plant and equipment
Insurance and property taxes
Total fixed factory overhead $ $ $
Total factory overhead $ $ $

Homework Answers

Answer #1
factory Overheads Budget
Budgeted DLH 9000 11000 13000
Variable overheads cost:
Indirect factory labor 87300 106700 126100
Power and light 3600 4400 5200
Indirect material 24300 29700 35100
Total Variable factory overheads 115200 140800 166400
Fixed factroy overheads cost:
Supervisory salaries 49280 49280 49280
Depreciation on Plant and Machinery 30980 30980 30980
Insurance and Property taxes 19710 19710 19710
Total Fixed factory overheads 99970 99970 99970
Total factory overheads 215170 240770 266370
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 13,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $93,600    Power and light 5,720    Indirect materials 35,100       Total variable overhead cost $134,420 Fixed overhead cost:    Supervisory salaries $47,050    Depreciation of plant and equipment 29,570    Insurance and property taxes 18,820       Total fixed overhead cost 95,440 Total factory...
Accounting pls Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department...
Accounting pls Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 11,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $106,700    Power and light 3,850    Indirect materials 34,100       Total variable overhead cost $144,650 Fixed overhead cost:    Supervisory salaries $50,630    Depreciation of plant and equipment 31,820    Insurance and property taxes 20,250       Total fixed overhead cost 102,700 Total factory overhead...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 9,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $64,800    Power and light 3,870    Indirect materials 20,700       Total variable overhead cost $89,370 Fixed overhead cost:    Supervisory salaries $31,280    Depreciation of plant and equipment 19,660    Insurance and property taxes 12,510       Total fixed overhead cost 63,450 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 9,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $79,200    Power and light 4,050    Indirect materials 21,600       Total variable overhead cost $104,850 Fixed overhead cost:    Supervisory salaries $36,700    Depreciation of plant and equipment 23,070    Insurance and property taxes 14,680       Total fixed overhead cost 74,450 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 9,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $85,500    Power and light 2,700    Indirect materials 21,600       Total variable overhead cost $109,800 Fixed overhead cost:    Supervisory salaries $38,430    Depreciation of plant and equipment 24,160    Insurance and property taxes 15,370       Total fixed overhead cost 77,960 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 16,000 hours of productive capacity in the department: Variable overhead costs:    Indirect factory labor $152,000    Power and light 7,200    Indirect materials 46,400       Total variable overhead cost $205,600 Fixed overhead costs:    Supervisory salaries $71,960    Depreciation of plant and equipment 45,230    Insurance and property taxes 28,780       Total fixed overhead cost 145,970 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 16,000 hours of productive capacity in the department: Variable overhead costs:    Indirect factory labor $137,600    Power and light 5,600    Indirect materials 35,200       Total variable overhead cost $178,400 Fixed overhead costs:    Supervisory salaries $62,440    Depreciation of plant and equipment 39,250    Insurance and property taxes 24,980       Total fixed overhead cost 126,670 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 14,000 hours of productive capacity in the department: Variable overhead costs:    Indirect factory labor $124,600    Power and light 4,900    Indirect materials 46,200       Total variable overhead cost $175,700 Fixed overhead costs:    Supervisory salaries $61,490    Depreciation of plant and equipment 38,650    Insurance and property taxes 24,600       Total fixed overhead cost 124,740 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 8,000 hours of productive capacity in the department: Variable overhead costs:    Indirect factory labor $78,400    Power and light 2,960    Indirect materials 25,600       Total variable overhead cost $106,960 Fixed overhead costs:    Supervisory salaries $37,440    Depreciation of plant and equipment 23,530    Insurance and property taxes 14,970       Total fixed overhead cost 75,940 Total factory...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $160,200    Power and light 5,940    Indirect materials 52,200       Total variable overhead cost $218,340 Fixed overhead cost:    Supervisory salaries $76,420    Depreciation of plant and equipment 48,030    Insurance and property taxes 30,570       Total fixed overhead cost 155,020 Total factory...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT