[The following information applies to the questions displayed below.]
A manufactured product has the following information for
June.
Standard | Actual | |||
Direct materials | 6 lbs. @ $8 per lb. | 44,800 | lbs. @ $8.20 per lb. | |
Direct labor | 3 hrs. @ $17 per hr. | 21,900 | hrs. @ $17.60 per hr. | |
Overhead | 3 hrs. @ $12 per hr. | $ | 272,900 | |
Units manufactured | 7,400 | |||
(1)
Compute the standard cost per unit.
(2) Compute the total cost variance for June.
Complete this question by entering your answers in the tabs below.
Compute the standard cost per unit.
|
Complete this question by entering your answers in the tabs below.
Compute the total cost variance for June. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.)
|
Direct Materials |
$48 |
6 lbs x $ 8 |
Direct Labor |
$51 |
3 hrs x $ 17 |
Overhead |
$36 |
3 hrs x $ 12 |
Total |
$135 |
Actual cost: |
||
Direct Materials |
$367,360 |
=44800*8.2 |
Direct Labor |
$385,440 |
=21900*17.6 |
Overhead |
$272,900 |
272900 |
Total Actual Cost |
$1,025,700 |
|
Total Standard cost |
$999,000 |
=7400*135 |
Total Cost Variance [$1025700 - 999000] |
$26,700 |
Unfavourable = Answer |