Question

Vaughn Mining Company recently purchased a quartz mine that it intends to work for the next...

Vaughn Mining Company recently purchased a quartz mine that it intends to work for the next 10 years. According to state environmental laws, Vaughn must restore the mine site to its original natural prairie state after it ceases mining operations at the site. To properly account for the mine, Vaughn must estimate the fair value of this asset retirement obligation. This amount will be recorded as a liability and added to the value of the mine on Vaughn’s books.

There is no active market for retirement obligations such as these, but Vaughn has developed the following cash flow estimates based on its prior experience in mining-site restoration. It will take 3 years to restore the mine site when mining operations cease in 10 years. Each estimated cash outflow reflects an annual payment at the end of each year of the 3-year restoration period.

Restoration Estimated Cash Outflow Probability Assessment

$15,980 10%

23,070 30%

23,570 50%

32,470 10%

What is the estimated fair value of Vaughn’s asset retirement obligation? Vaughn determines that the appropriate discount rate for this estimation is 5%. (Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 458,581.) Estimated fair value of Vaughn’s asset retirement obligation $

Homework Answers

Answer #1

Estimated fair value of Vaughn’s asset retirement obligation

Estimated fair value of Vaughn’s asset retirement obligation is the Present Value of the Expected cash outflow of the mining operation

Step – 1, Calculation of Expected Cash Outflow of the mining operation

Expected Cash outflow = Sum [Cash outflow x Probability]

= [$15,980 x 10%] + [$23,070 x 30%] + [$23,570 x 50%] + [$32,470 x 10%]

= $1,598 + 6,921 + 11,785 + 3,247

= $23,551

Step – 2, Estimated fair value of Vaughn’s asset retirement obligation

Estimated fair value of Vaughn’s asset retirement obligation = Present Value of Expected Cash Outflows

= $23,551 x [PVIF 5%, 10 Years]

= $23,551 / (1 + r) n

= $23,551 / (1 + 0.05) 10

= $23,551 / 1.62889

= $14,458 (Rounded to 0 decimal places)

“Hence, Estimated fair value of Vaughn’s asset retirement obligation = $14,458”

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem 6-15 Incorrect answer. Your answer is incorrect. Try again. Tamarisk Mining Company recently purchased a...
Problem 6-15 Incorrect answer. Your answer is incorrect. Try again. Tamarisk Mining Company recently purchased a quartz mine that it intends to work for the next 10 years. According to state environmental laws, Tamarisk must restore the mine site to its original natural prairie state after it ceases mining operations at the site. To properly account for the mine, Tamarisk must estimate the fair value of this asset retirement obligation. This amount will be recorded as a liability and added...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,850,000 in 2021...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,850,000 in 2021 for the mining site and spent an additional $770,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,800,000 in 2021...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,800,000 in 2021 for the mining site and spent an additional $760,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
On January 1, 2016, Barbosa Company purchased a coal mining site for $1,000,000. Under the terms...
On January 1, 2016, Barbosa Company purchased a coal mining site for $1,000,000. Under the terms of the purchase agreement, Barbosa must restore the site to specified conditions at an estimated cost of $125,000. Barbosa estimates that it will be able to operate the site for 20 years. Barbosa uses a 6% discount rate and a straight-line method of depreciation. Required: 1. Prepare the journal entry necessary to record the purchase of the coal mining site. 2. Prepare any journal...
Salter Mining Company purchased the Northern Tier Mine for $77 million cash. The mine was estimated...
Salter Mining Company purchased the Northern Tier Mine for $77 million cash. The mine was estimated to contain 9.17 million tons of ore and to have a residual value of $6.7 million. During the first year of mining operations at the Northern Tier Mine, 80,000 tons of ore were mined, of which 14,000 tons were sold. a. Prepare a journal entry to record depletion during the year. b. Show how the Northern Tier Mine, and its accumulated depletion, would appear...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,600,000 in 2018...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,600,000 in 2018 for the mining site and spent an additional $720,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Exercise 3: Depletion The Stewart Mining Company operates a copper mine. The company paid $10,000,000 in...
Exercise 3: Depletion The Stewart Mining Company operates a copper mine. The company paid $10,000,000 in 2018 for the mining site and spent an additional $1,000,000 to prepare the mine for extraction of the copper. After extracting the copper, the company is required to restore the land to its original condition. The present value of the restoration costs is $2,000,000. There will be no residual (salvage) value for the copper mine. The company also purchased new equipment in 2018 for...
Smithson Mining operates a silver mine in Nevada. Acquisition, exploration, and development costs totaled $6.8 million....
Smithson Mining operates a silver mine in Nevada. Acquisition, exploration, and development costs totaled $6.8 million. After the silver is extracted in approximately five years, Smithson is obligated to restore the land to its original condition, including constructing a wildlife preserve. The company’s controller has provided the following three cash flow possibilities for the restoration costs: (1) $620,000, 15% probability; (2) $670,000, 45% probability; and (3) $770,000, 40% probability. The company’s credit-adjusted, risk-free rate of interest is 8%. (FV of...
Sweet Mining Company purchased land on February 1, 2020, at a cost of $856,800. It estimated...
Sweet Mining Company purchased land on February 1, 2020, at a cost of $856,800. It estimated that a total of 53,100 tons of mineral was available for mining. After it has removed all the natural resources, the company will be required to restore the property to its previous state because of strict environmental protection laws. It estimates the fair value of this restoration obligation at $97,200. It believes it will be able to sell the property afterwards for $108,000. It...
Swifty Mining Company purchased land on February 1, 2020, at a cost of $996,100. It estimated...
Swifty Mining Company purchased land on February 1, 2020, at a cost of $996,100. It estimated that a total of 51,900 tons of mineral was available for mining. After it has removed all the natural resources, the company will be required to restore the property to its previous state because of strict environmental protection laws. It estimates the fair value of this restoration obligation at $93,600. It believes it will be able to sell the property afterwards for $104,000. It...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT