12)
Lakeside Inc. manufactures four lines of remote control boats
and uses activity-based costing to calculate product
cost.
Activity Cost Pools | Estimated Total Cost | Estimated Cost Driver | ||
Machining | $ | 317,000 | 13,900 | machine hours |
Setup | 61,000 | 250 | batches | |
Quality control | 85,000 | 880 | inspections | |
Suppose the Speedy boat requires 2,300 machine hours, 94 batches, and 260 inspections. Using the activity rates, determine the amount of overhead assigned to the Speedy product line. (Round intermediate calculations to 2 decimal places and your final answers to the nearest dollar amount.)
STATEMENT SHOWING ACTIVITY RATE OF ACTIVITY POOL | ||||||||
Activity | Total | Expected | Activity | |||||
ACTIVITY COST POOL | Measures | Overheads | Activity | Rate | ||||
Machining | MH | 317,000 | 13,900 | 22.81 | per MH | |||
Setup | Batches | 61,000 | 250 | 244.00 | Per batch | |||
Quality control | Inspections | 85,000 | 880 | 96.59 | Per Inspection | |||
Activity cost for Speddy Product line: | ||||||||
Machining | (2300*22.81) | 52463 | ||||||
Setup | (94*244) | 22936 | ||||||
Quality control | (260*96.59) | 25113.4 | ||||||
Total activity cost | 100512.4 |