Question

A project with a calculated payback period of 3.7 means the payback period is rounded a....

A project with a calculated payback period of 3.7 means the payback period is rounded
a. four years
b. three years and five months
c. three years and nine months
d. three years and seven months

Homework Answers

Answer #1

Payback period = 3.7 years

This means that the payback period is three years and some additional months. The additional months will be calculated by dividing the actual months by 12.

Therefore 0.70 represents 8.5 months which some less than 9 months and as the rounding off the digit will consider then it will be 9 months.

= 8.5/12

= 0.70

Therefore 3.7 years of payback period means three years and nine months.

Therefore the correct option is C

If you find the answer helpful please upvote.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The payback period for a project is often calculated and then a decision about undertaking the...
The payback period for a project is often calculated and then a decision about undertaking the project is made after comparing this calculated payback period to a target payback period. Select all characteristics that apply to the target payback period. The target payback period: is usually determined by management. can be expressed as a range of acceptable periods. is irrelevant if the payback period for the project is less than three years. is a number calculated as a fixed percentage...
What is the payback period for a project with an initial investment of $90,000 that provides...
What is the payback period for a project with an initial investment of $90,000 that provides an annual cash inflow of $20,000 for the first three years and $12500 per year for years four and five, and $25000 per year for years six through eight?
Project A has a net present value of $1,500, a payback period of 2 years, and...
Project A has a net present value of $1,500, a payback period of 2 years, and an internal rate of return of 12%.  Project B has a net present value of $1,800, a payback period of 4 years, and an internal rate of return of 10%.  Project C has a netpresent value of $1,750, a payback period of 3 years, and an internal rate of return of 11%.  If the projects are mutually exclusive, which project should be undertaken? A. Project A because...
Calculate payback period and discounted payback period for the following project if the discount rate is...
Calculate payback period and discounted payback period for the following project if the discount rate is 10% The initial outlay or cost for a four-year project is $1,300,000. The respective cash inflows for years 1, 2, 3 and 4 are: $700,000, $500,000,$500,000 and $300,000.
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$80,000 and expected free cash flows of ​$26,000 at the end of each year for 6 years. The required rate of return for this project is 7 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​? a. The​ project's payback period is nothing years.  ​(Round...
Diana usually uses a three-year payback period to determine if a project is acceptable. A recent...
Diana usually uses a three-year payback period to determine if a project is acceptable. A recent project with uniform yearly savings over a five-year life had a payback period of almost exactly three years, so Diana decided to find the project's present worth to help determine if the project was truly justifiable. However, that calculation didn't help either since the present worth was exactly 0. What interest rate was Diana using to calculate the present worth? The project has no...
7. The NPV and payback period Suppose you are evaluating a project with the cash inflows...
7. The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 $350,000 Year 2 600,000 Year 3 600,000 Year 4 450,000 If the project’s desired...
What information does the payback period provide? Suppose Praxis Corporation’s CFO is evaluating a project with...
What information does the payback period provide? Suppose Praxis Corporation’s CFO is evaluating a project with the following cash inflows. She does not know the project’s initial cost; however, she does know that the project’s regular payback period is 2.5 years. Year Cash Flow Year 1 $300,000 Year 2 $450,000 Year 3 $400,000 Year 4 $450,000 If the project’s weighted average cost of capital (WACC) is 10%, what is its NPV? A.) $302,510 B.) $332,761 C.) $317,636 D.) $287,385 Which...
11. The NPV and payback period What information does the payback period provide? A project’s payback...
11. The NPV and payback period What information does the payback period provide? A project’s payback period (PB) indicates the number of years required for a project to recover its initial investment using its operating cash flows. As the theoretical soundness of the conventional (undiscounted) PB technique was criticized, the model was modified to incorporate the time value of money-adjusted operating cash flows to create the discounted payback method. While both payback models continue to reflect faulty ranking criteria, they...
The NPV and payback period Suppose you are evaluating a project with the cash inflows shown...
The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 $400,000 Year 2 600,000 Year 3 500,000 Year 4 475,000 If the project’s desired rate...