Shire Computer’s
predetermined overhead rate is based on direct labor cost.
Management estimates the company will incur $747,500 of overhead
costs and $575,000 of direct labor cost for the year. During March,
Shire began and completed Job 13-56.
Complete this question by entering your answers in the tabs below.
What is the predetermined overhead rate for the year?
|
Complete this question by entering your answers in the tabs below.
Using the information on the following job cost sheet, determine the total cost of the job.
|
Solution 1:
Overhead Rate | ||||
Choose Numerator: | / | Choose Denominator: | = | Overhead Rate |
Estimated overhead | / | Estimated direct labor costs | = | Overhead rate |
747500 | / | 575000 | = | 130% |
Solution 2:
Job Cost Sheet Job 13-56 | ||||||
Direct Materials | Direct labor | Overhead | Total Costs | |||
Date | Requisition No. | Amount | Time Ticket No. | Amount | Costs Applied | |
8-march | 4-129 | $5,000 | T-306 | $700 | $910 | |
11-march | 4-142 | $7,020 | T-432 | $1,250 | $1,625 | |
18-march | 4-167 | $3,330 | T-456 | $1,250 | $1,625 | |
$15,350 | $3,200 | $4,160 | $22,710 |