Angus Corp. acquires land for $105,000 cash. Additional costs are as follows: Removal of shed $...

Angus Corp. acquires land for $105,000 cash. Additional costs are as follows:

Removal of shed $ 500
Filling and grading 3,200
Residual value of lumber from shed 150
Paving of parking lot 16,000
Closing costs 1,350


Angus will record the cost of the land as

Homework Answers

Answer #1

Cost of the land = $109,900

Explanation

Cost of Land
$ $
Cost of purchases of land     105,000.00
Add:
Removal of shed              500.00
Filling and grading            3,200.00
Closing costs            1,350.00        5,050.00
    110,050.00
Less: Residual value of lumber from shed         (150.00)
Total cost of land 109,900.00
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT