Angus Corp. acquires land for $105,000 cash. Additional costs
are as follows:
Removal of shed | $ 500 |
Filling and grading | 3,200 |
Residual value of lumber from shed | 150 |
Paving of parking lot | 16,000 |
Closing costs | 1,350 |
Angus will record the cost of the land as
Cost of the land = $109,900
Explanation
Cost of Land | ||
$ | $ | |
Cost of purchases of land | 105,000.00 | |
Add: | ||
Removal of shed | 500.00 | |
Filling and grading | 3,200.00 | |
Closing costs | 1,350.00 | 5,050.00 |
110,050.00 | ||
Less: Residual value of lumber from shed | (150.00) | |
Total cost of land | 109,900.00 |