Question

Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...

Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:


  Inspection time 0.4 days
  Wait time (from order to start of production) 17.0 days
  Process time 3.1 days
  Move time 1.1 days
  Queue time 4.2 days


Required:
1.

Compute the throughput time. (Round your answer to 1 decimal place.)

     

2.

Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.)

     

3.

What percentage of the throughput time was spent in non–value-added activities? (Round your percentage answer to nearest whole percent.)

     

4.

Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)

     

5.

If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your percentage answer to nearest whole percent.)

     

Homework Answers

Answer #1

· Requirements asked

1

Throughput time

8.8

days

2

Manufacturing Cycle Efficiency (MCE)

35%

3

Non Value added throuput time

65%

4

Delivery Cycle time

25.8

days

5

New MCE

67.4%

· Workings

A

Inspection time

0.4

days

B

Wait time

17

days

C

Process time

3.1

days

D

Move Time

1.1

days

E

Queue time

4.2

days

F = A+C+D+E

Throughput time

8.8

days = Requirement 1

G = C/F

Manufacturing Cycle Efficiency (MCE)

35%

Requirement 2

H = 100% - G

Percentage of throughput time spent

65%

Requirement 3

I = B + F

Delivery Cycle time

25.8

days = Requirement 4

J = C/(A+C+D)

New MCE

67.4%

Requirement 5

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.2 days Wait time (from order to start of production) 15.4 days Process time 3.3 days Move time 1.3 days Queue time 4.1 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.8 days Wait time (from order to start of production) 15.3 days Process time 3.3 days Move time 1.5 days Queue time 4.4 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 16.2 days Process time 3.2 days Move time 1.5 days Queue time 4.0 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 15.7 days Process time 2.9 days Move time 0.8 days Queue time 3.6 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 16.7 days Process time 3.0 days Move time 1.5 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 15.9 days Process time 2.7 days Move time 1.2 days Queue time 3.5 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.8 days Wait time (from order to start of production) 15.2 days Process time 3.1 days Move time 0.9 days Queue time 3.5 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.4 days Wait time (from order to start of production) 16.0 days Process time 2.5 days Move time 0.8 days Queue time 4.4 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 16.0 days Process time 2.5 days Move time 1.5 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 14.0 days Process time 2.7 days Move time 1.0 days Queue time 5.0 days Required: 1. Compute the throughput time. 2. Compute the manufacturing...