Question

“Don’t tell me we have lost another bid!” exclaimed Roha, president of Rohami Sdn Bhd. “I’m...

“Don’t tell me we have lost another bid!” exclaimed Roha, president of Rohami Sdn Bhd. “I’m afraid so,” replied Ramy, the operation vice president. “One of our competitors underbid us by about RM10,000 on the RR2 job.” “I just can’t figure it out,” said Roha. “It seems we are either too high to get the job or too low to make any money on half the jobs we bid any more. What’s happened?”

Roha Sdn Bhd manufactures specialized goods to customers’ specifications and operates a job-order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the year:

Department

Cutting

Machining

Assembly

Total Plant

Direct labor

RM300,000

RM200,000

RM400,000

RM900,000

Manufacturing overhead

RM540,000

RM800,000

RM100,000

RM1,440,000

  

Jobs require varying amounts of work in the three departments. The RR2 job, for example, would have required manufacturing costs in the three departments as follows:

Department

Cutting

Machining

Assembly

Total Plant

Direct materials

RM12,000

RM900

RM5,600

RM18,500

Direct labor

RM6,500

RM1,700

RM13,000

RM21,200

Manufacturing overhead

?

?

?

?

The company uses a plantwide overhead rate to apply manufacturing overhead cost to jobs.

REQUIRED:

(a) Assuming use of a plantwide overhead rate:

(i) Compute the rate for the current year.

(ii) Determine the amount of manufacturing overhead cost that would have been applied to the RR2 job.

(b) Suppose that instead of using a plantwide overhead rate, the company had used a separate predetermined overhead rate in each department. Under these conditions:

(i) Compute the rate for each department for the current year.

(ii) Determine the amount of manufacturing overhead cost that would have been applied to the RR2 job.

(c) Explain the difference between the manufacturing overhead that would have been applied to RR2 job using the plantwide rate in part (a) (ii) above and using the departmental rates in part (b) (ii).

(d) Assume that it is necessary in the industry to bid jobs at 150% of total manufacturing cost. What was the company’s bid price on the RR2 job if a plantwide overhead rate is used? What would the bid price have been if departmental overhead rates had been used to apply overhead cost?

(e) At the end of the year, the company assembled the following actual cost data relating to all jobs worked on during the year:

Department

Cutting

Machining

Assembly

Total Plant

Direct materials

RM760,000

RM90,000

RM410,000

RM1,260,000

Direct labor

RM320,000

RM210,000

RM340,000

RM870,000

Manufacturing overhead

RM560,000

RM830,000

RM92,000

RM1,482,000

Compute the underapplied or overapplied overhead for the year:

  1. Assuming that a plantwide overhead rate is used.
  2. Assuming that departmental overhead rates are used.

Homework Answers

Answer #1

a) Using plantwide overhead rate

Overhead Recovery Rate = Manufacturing Overhead/ total direct labour
Overhead Recovery Rate = 1440,000/900,000 = $1.6 per labour hour
RR2 Job Costing Machining Machining Assembly Total
Direct Material               12,000                       900                 5,600            18,500
Direct Labour                 6,500                   1,700               13,000            21,200
Mfg Ovhs ($1.6* Direct labour)               10,400                   2,720               20,800            33,920
Total Cost               28,900                   5,320               39,400            73,620

b)

Pre-determined overhead rate in each department
Machining Machining Assembly Total
Direct Labour (A)             300,000              200,000            400,000          900,000
Manufacturing Overhead (B)             540,000              800,000            100,000      1,440,000
Overhead recovery rate (B/A)                    1.80                     4.00                   0.25
RR2 Job Costing Machining Machining Assembly Total
Direct Material               12,000                       900                 5,600            18,500
Direct Labour                 6,500                   1,700               13,000            21,200
Mfg Ovhs (Rate* Direct labour)               11,700                   6,800                 3,250            21,750
Total Cost               30,200                   9,400               21,850            61,450

C)

Differnce in between Mfg Ovhs               (1,300)                 (4,080)               17,550            12,170
(10400-11700) (2720-6800) (20800-3250)

D)

Bid Price = 150% of total cost
Total Cost Bid Price
Using plantwide overhead rate               73,620              110,430
Pre-determined ovh rate in each dept               61,450                 92,175

E)

Using plantwide overhead rate Budgeted Actual Variance -Over/(under)
Machining Machining Assembly Total Machining Machining Assembly Total Machining Machining Assembly Total
Direct Labour             300,000              200,000            400,000          900,000           320,000           210,000        340,000        870,000       (20,000)        (10,000)         60,000      30,000
Mfg Ovhs ($1.6* Direct labour)             480,000              320,000            640,000      1,440,000           560,000           830,000           92,000    1,482,000       (80,000)      (510,000)      548,000    (42,000)
Total Cost             780,000              520,000         1,040,000      2,340,000           880,000       1,040,000        432,000    2,352,000    (100,000)      (520,000)      608,000    (12,000)
Pre-determined ovh rate in each dept Budgeted Actual Variance -Over/(under)
Machining Machining Assembly Total Machining Machining Assembly Total Machining Machining Assembly Total
Direct Labour             300,000              200,000            400,000          900,000           320,000           210,000        340,000        870,000       (20,000)        (10,000)         60,000      30,000
Manufacturing Overhead             540,000              800,000            100,000      1,440,000           560,000           830,000           92,000    1,482,000       (20,000)        (30,000)           8,000    (42,000)
Total Cost             840,000           1,000,000            500,000      2,340,000           880,000       1,040,000        432,000    2,352,000       (40,000)        (40,000)         68,000    (12,000)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
"Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm...
"Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm afraid so," replied Doug Martin, the operations vice president. "One of our competitors underbid us by about $9,800 on the Hastings job." "I just can’t figure it out," said Kovallas. "It seems we’re either too high to get the job or too low to make any money on half the jobs we bid anymore. What’s happened?"      Lenko Products manufactures specialized goods to customers'...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...
"Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm...
"Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm afraid so," replied Doug Martin, the operations vice president. "One of our competitors underbid us by about $9,800 on the Hastings job." "I just can’t figure it out," said Kovallas. "It seems we’re either too high to get the job or too low to make any money on half the jobs we bid anymore. What’s happened?"      Lenko Products manufactures specialized goods to customers'...
"Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm...
"Don't tell me we've lost another bid!" exclaimed Sandy Kovallas, president of Lenko Products, Inc. "I'm afraid so," replied Doug Martin, the operations vice president. "One of our competitors underbid us by about $10,100 on the Hastings job." "I just can’t figure it out," said Kovallas. "It seems we’re either too high to get the job or too low to make any money on half the jobs we bid anymore. What’s happened?"      Lenko Products manufactures specialized goods to customers'...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 500,000 $ 100,000 $ 600,000 Direct labor hours 10,000 50,000 60,000 Machine hours 50,000 5,000 55,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 9,522,000 $ 529,000 $ 10,051,000 Direct labor hours 23,000 414,000 437,000 Machine hours 414,000 18,000 432,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 18,032,000 $ 784,000 $ 18,816,000 Direct labor hours 28,000 644,000 672,000 Machine hours 644,000 23,000 667,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
The Kristopher Company uses a job-costing system at its plant. The plant has a Machining Department...
The Kristopher Company uses a job-costing system at its plant. The plant has a Machining Department and an Assembly Department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the Machining Department overhead, allocated to jobs based on actual machine-hours, and the Assembly Department overhead, allocated to jobs based on actual direct manufacturing labor cost). The 2019 budget for the plant is: Machining Assembly Manufacturing overhead $1,800,000 $3,600,000 Direct manufacturing...
Assume that Mason Company uses departmental predetermined overhead rates. The Machining Department is allocated based on...
Assume that Mason Company uses departmental predetermined overhead rates. The Machining Department is allocated based on machine-hours and the Assembly Department is allocated based on direct labor-hours. How much manufacturing overhead cost would be applied to Job A? Job B? Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT