Question

At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is...

At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units.

The following data relate to these two jobs:

On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $10 per unit and 1,500 units for Job 42 at $14 per unit.

During August, Prichard Company accumulated 400 hours of direct labor costs on Job 40 and 1,200 hours on Job 42. The total direct labor was incurred at a rate of $24 per direct labor hour for Job 40 and $10 per direct labor hour for Job 42.

The predetermined factory overhead rate is $8.00 per direct labor hour.

a. Determine the balance on the job cost sheets for Jobs 40 and 42 at the end of August.

Job 40 $
Job 42 $

b. Determine the cost per unit for Jobs 40 and 42 at the end of August. If required, round your answers to the nearest cent.

Job 40 $
Job 42 $

Homework Answers

Answer #1
  • [a]

Job 40

$16,800

Job 42

$42,600

  • [b]

Job 40

$84.00

Job 42

$85.20

  • Workings

Job 40

Job 42

Direct material cost

$4,000

$21,000

Direct Labor Cost

$9,600

$12,000

Overhead applied

$3,200

$9,600

A

Balance on Job Cost sheet

$16,800

$42,600

B

No of units

200

500

C = A/B

Cost per unit

$84.00

$85.20

Job 40

Job 42

Direct material cost

=400*10

=1500*14

Direct Labor Cost

=400*24

=1200*10

Overhead applied

=400*8

=1200*8

A

Balance on Job Cost sheet

$16,800

$42,600

B

No of units

200

500

C = A/B

Cost per unit

=16800/200

=42600/500

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is...
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is for 500 units, and Job 42 is for 200 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $18 per unit and 900 units for Job 42 at $20 per unit. During August, Darling Company accumulated 600 hours of direct labor costs on Job 40 and 1,100...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $16 per unit and 1,000 units for Job 42 at $24 per unit. During August, Prichard Company accumulated 600 hours of direct labor costs on Job 40...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 200 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,400 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 300 hours of direct labor costs on Job 40...
At the end of April, Ingram Company had completed Jobs 50 and 51. Job 50 is...
At the end of April, Ingram Company had completed Jobs 50 and 51. Job 50 is for 1,000 units, and Job 51 is for 500 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 500 units for Job 50 at $18 per unit and 1,400 units for Job 51 at $18 per unit. During April, Ingram Company accumulated 400 hours of direct labor costs on Job 50 and 700...
At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is...
At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 200 units, and Job 51 is for 2,000 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 600 units for Job 50 at $24 per unit and 900 units for Job 51 at $18 per unit. During April, Kaye Company accumulated 200 hours of direct labor costs on Job 50 and 400...
1. Carrothers Company estimates that total factory overhead costs will be $960,000 for the year. Direct...
1. Carrothers Company estimates that total factory overhead costs will be $960,000 for the year. Direct labor hours are estimated to be 80,000. a. For Carrothers Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. ___________ per direct labor hour b. During August, Carrothers Company accumulated 4,300 hours of direct labor costs on Job 50 and 5,100 hours on Job 56. Determine the amount of factory overhead applied to Jobs 50 and 56 in...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of the March and Job Q was incomplete at the end of the March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Direct Labor Costs During August, Hatch Company accumulated 610 hours of direct labor costs on Job...
Direct Labor Costs During August, Hatch Company accumulated 610 hours of direct labor costs on Job 40 and 890 hours on Job 42. The total direct labor was incurred at a rate of $20 per direct labor hour for Job 40 and $25 per direct labor hour for Job 42. Journalize the entry to record the flow of labor costs into production during August.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT