Question

A company has the following information for Job Alpha during July: Units produced              257 Actual...

  1. A company has the following information for Job Alpha during July:

Units produced

             257

Actual materials used

          1,722

lbs.

Actual materials cost

$         5.85

per lb.

Actual labor hours incurred

             771

Actual labor rate

$      14.25

per hour

Work in process, July 1

$      4,000

Work in process, July 31

$             -  

The company applies manufacturing overhead to jobs based on direct labor hours.

Additional information for the company in July is as follows:

Total estimated labor hours

          2,170

Standard materials per unit

7

lbs.

Standard materials cost

$         5.50

per lb.

Standard labor hours per unit

2.80

Standard labor rate

$      15.00

per hour

Standard variable overhead

$         3.00

per labor hour

Standard fixed overhead

$         2.00

per labor hour

    *based on 35,000 labor hours

Actual total output in units

             755

Actual total labor hours

          2,454

Actual variable overhead

$         3.40

per labor hour

Actual total fixed overhead

$      4,040

  1. Calculate the July direct labor flexible budget variance for Job Alpha:
  2. Calculate the July labor rate variance for Job Alpha :
  3. Calculate the labor efficiency variance for Job Alpha in

Homework Answers

Answer #1
Req a.
Labour flexible budget variance
Std hours allowed (257*2.80) 719.6
Multiply: Std rate 15
Std labour cost 10794
Actual labour cost (771*14.25) 10986.75
Labour flexible budget variance 192.75 unfav
Req b.
labour rate variance = Actual hours (Std rate -Actual rate )
771 (15-14.25) = 578.25 Fav
Req c.
Labour efficiency variance = Std rate (Std hours -Actual hours )
15.00 (719.60- 771) = 771 Unfav
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
The following information describes production activities of Mercer Manufacturing for the year. Actual direct materials used...
The following information describes production activities of Mercer Manufacturing for the year. Actual direct materials used 33,000 lbs. at $5.90 per lb. Actual direct labor used 10,700 hours for a total of $221,490 Actual units produced 63,000 Budgeted standards for each unit produced are 0.50 pounds of direct material at $5.85 per pound and 10 minutes of direct labor at $21.70 per hour. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price AH...
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per...
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per unit @ $12.50 per lb. Direct labor 0.5 hours per unit @ $96 per hour Overhead $132 per direct labor hour Units manufactured 16,000 Total manufacturing costs $ 2,216,400 (1) Compute the standard cost per unit. (2) Compute the total budgeted cost for production in August. (3) Compute the total cost variance for August. (Indicate the effect of each variance by selecting for favorable,...
The following data relates to Potawatomi Corporation's operations for the month. Potawatomi produced 8,500 units and...
The following data relates to Potawatomi Corporation's operations for the month. Potawatomi produced 8,500 units and the normal monthly capacity is 20,000 direct labor hours. Standard Unit Costs Total Actual Costs Direct Material:          Standard (5 lbs. @ $2.10/lb.) $10.50          Actual (39,000 lbs. @ $2.20/lb.) $85,800 Direct Labor:         Standard (2 hrs. @ $12/hr.) $24.00         Actual (18,000 hrs. @ $11.90/hr.) $214,200 Variable Overhead:         Standard (2 hrs. @ $4.00/hr.) $8.00         Actual $69,700                Total $42.50 $369,700 Calculate...
Required information [The following information applies to the questions displayed below.] A manufactured product has the...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 7 lbs. @ $8 per lb. 62,900 lbs. @ $8.10 per lb. Direct labor 3 hrs. @ $17 per hr. 26,400 hrs. @ $17.50 per hr. Overhead 3 hrs. @ $13 per hr. $ 352,500 Units manufactured 8,900 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance...
Abbeville Fixture Company manufactures units in a small manufacturing facility. The units are made from brass....
Abbeville Fixture Company manufactures units in a small manufacturing facility. The units are made from brass. Manufacturing has 50 employees. Each employee presently provides 40 hours of labor per week. Information about a production week is as follows: Standard wage per hour $14.4 Standard labor time per unit 20 min. Standard number of lbs. of brass 2.1 lbs. Standard price per lb. of brass $9.75 Actual price per lb. of brass $10 Actual lbs. of brass used during the week...
A manufactured product has the following information for June.
A manufactured product has the following information for June.StandardActualDirect materials5 lbs. @ $8 per lb.38,000lbs. @ $8.10 per lb.Direct labor3 hrs. @ $16 per hr.22,200hrs. @ $16.40 per hr.Overhead3 hrs. @ $11 per hr.$252,700Units manufactured7,500(1) Compute the standard cost per unit.(2) Compute the total cost variance for June.Direct materials :Direct labor:Overhead:Total :Total cost variance:
A manufactured product has the following information for June.
A manufactured product has the following information for June.StandardActualDirect materials5 lbs. @ $8 per lb.38,000lbs. @ $8.10 per lb.Direct labor3 hrs. @ $16 per hr.22,200hrs. @ $16.40 per hr.Overhead3 hrs. @ $11 per hr.$252,700Units manufactured7,500(1) Compute the standard cost per unit.(2) Compute the total cost variance for June.Direct materials :Direct labor:Overhead:Total :Total cost variance:
#11 Direct Materials and Direct Labor Variance Analysis Abbeville Fixture Company manufactures units in a small...
#11 Direct Materials and Direct Labor Variance Analysis Abbeville Fixture Company manufactures units in a small manufacturing facility. The units are made from brass. Manufacturing has 40 employees. Each employee presently provides 40 hours of labor per week. Information about a production week is as follows: Standard wage per hour $12.6 Standard labor time per unit 20 min. Standard number of lbs. of brass 1.7 lbs. Standard price per lb. of brass $11 Actual price per lb. of brass $11.25...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT