Question

Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)      &nbsp

Consider the following table:

ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)         

to           tml                tp                                 te

    A                     -----                        1                      2                      3                      

    B                      A                           2                      4                      6

    C                      B                            1                      4                      7

    D                      B                            3                      4                      5

    E                      C                            1                      3                      5

    F                      D, E                       2                      3                      4

1) Construct a PERT network.

[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.

3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest hundredth: two decimal places.  

4) What is the completion time at 95% confidence level?

5) What is the likelihood of this project being completed earlier than 14 days?

6) Between 13 and 15 days?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4...
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4 5 4 B - 5 8 11 8 C A 1 2 3 2 D B 2 5 8 5 E B 4 6 8 6 F C,D 1 1 1 1 G E 3 4 5 4 H G,F 2 3 4 3 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What is the slack of activity B? 8 0 3 2 7
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. CAN ONLY BE ONE OF THE OPTIONS it's not 5 I tried that. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What...
Assume that activity F has the following times: Early start time (ES) = 7 days Early...
Assume that activity F has the following times: Early start time (ES) = 7 days Early finish time (EF) = 13 days Latest start time (LS) = 15 days Latest finish time (LF) = 21 days Which of the following statements is TRUE about activity F? Activity F takes 14 days to complete Activity F is on the critical path Activity F has 8 days of slack time Activity F is the first activity of the project None of the...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Use the following table to answer the following question Activity Immediate Predecessor Time ES EF LS...
Use the following table to answer the following question Activity Immediate Predecessor Time ES EF LS LF A - 4 0 4 6 10 B - 5 0 5 0 5 C A 3 4 7 10 13 D B 8 5 13 5 13 E B 2 5 7 16 18 F C, D 3 13 16 15 18 G C, D 7 13 20 13 20 H E, F 2 16 18 18 20 How long can activity...