Demi Delights manufactures specialtys chocolate bars X, Y and Z,whichshebelieveswillappealtotheyoungergenerationofconsumers.Thecontributionmarginsforthebarsare$0.40, $0.50 and$1.00 respectively .Demi Delights faces...

Demi Delights manufactures specialtys chocolate bars X, Y and Z,whichshebelieveswillappealtotheyoungergenerationofconsumers.Thecontributionmarginsforthebarsare$0.40, $0.50 and$1.00 respectively .Demi Delights faces the problem of having only 2500 machine hours available per month. Each batch needs to use the same machine for processing;the hours required for each of the products are 1, 1 and 5 hours respectively. Demand for product X is 500, Y is 1,500 and Z is 1,000.How many units of each product will the firm produce?

A.1000 Z

B. 500X,1,500 Y and 1,000Z

C.500 X,1,500 Y and 100Z

D.500 X and 1,500Y

Homework Answers

Answer #1
Since machine hours is the constraint, the contribution margin per machine hour should be used to priortise production
X Y Z
Contribution margin per unit 0.4 0.5 1
Machine hours required per unit 1 1 5
Contribution margin per machine hour 0.4 0.5 0.2
Production Schedule
Product Units Machine hours per unit Total machine hours
X 500 1 500
Y 1500 1 1500
Z 100 5 500
Total 2500
Hence, the answer is C. C.500 X,1,500 Y and 100Z
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Duck Company makes three products (X, Y, & Z) with the following characteristics: Products X Y...
Duck Company makes three products (X, Y, & Z) with the following characteristics: Products X Y Z Selling price per unit $ 10 $ 15 $ 20 Variable cost per unit $ 6 $ 10 $ 10 Machine hours per unit 2 4 10 The company has a capacity of 2,000 machine hours, but there is virtually unlimited demand for each product. In order to maximize total contribution margin, how many units of each product should the company produce? Multiple...
ABC Company produces Product X, Product Y, and Product Z. All three products require processing on...
ABC Company produces Product X, Product Y, and Product Z. All three products require processing on specialized finishing machines. The capacity of these machines is 2,250 hours per month. ABC Company wants to determine the product mix that should be achieved to meet the high demand for each product and provide the maximum profit. Following is information about each product: Product X Product Y Product Z Selling price $ 150 $ 118 $ 39 Variable costs 105 58 28 Machine...
Brenda’s Brakes manufactures three different product lines, Models X, Y, and Z. The following per unit...
Brenda’s Brakes manufactures three different product lines, Models X, Y, and Z. The following per unit data apply:                                                                                     Model X        Model Y        Model Z          Selling price                                                         $50                 $60                 $70          Direct materials                                                        6                      6                      6          Direct labour ($12 per hour)                                12                    18                    24          Variable support costs ($4 per machine hour)   4                      6                      8          Fixed costs                                                             10                    10                    10 Required: If there are a limited number of direct labour hours available and demand exceeds the...
Orange County Chrome Company manufactures three chrome-plated products—automobile bumpers, valve covers, and wheels. These products are...
Orange County Chrome Company manufactures three chrome-plated products—automobile bumpers, valve covers, and wheels. These products are manufactured in two production departments (Stamping and Plating). The factory overhead for Orange County Chrome is $213,389. The three products consume both machine hours and direct labor hours in the two production departments as follows: Direct Labor Hours Machine Hours Stamping Department Automobile bumpers 558 803 Valve covers 295 557 Wheels 340 597 1,193 1,957 Plating Department Automobile bumpers 171 1,166 Valve covers 175...
Assessment Module 9 – Marginal Analysis Please create a tab in your Excel Workbook and name...
Assessment Module 9 – Marginal Analysis Please create a tab in your Excel Workbook and name it “Module 9 Marginal Analysis.” You have same basic templates in your Resources workbook, but you may need to modify these to fit the individual business problem. I am evaluating your professional ability to do so, and to create professional models and reports, so take your time, think through a logical, clear, well-structured, well-formatted model. Remember, assumption tables (like T-accounts) are your friends! Be...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT